Slice Test - Check and connectorisation of the cables

  1. Take the test sheet of the slot under investigation
  2. Check the cables of the TELL1 in crate D3E02U, D3E02L, D3E03U, D3E03L or D3E04U. The ports of the TELL are numbered from PP0 (top) to PP3 (bottom).
  3. Check the cable in the given channel of the Control Board in crate ??? or ??? (balcony). The Control Board channels range from channel 0 (top) to channel 5 (bottom).
  4. Move to the VELO A- (close to the elevator) or C-side (cloe to the cryogenics platform).
  5. Check that the LV of the hybrid and the Repeater Board are switched off, i.e. check that the current ??? does not exceed ??? V.
  6. Carefully remove the cables of the last slot.
  7. Carefully connect the cables of the slot under test. The control cable is connected to the middle port (J21), the data cables to the upper (J17, J18) and lower (J19, J20) two ports.

Attention

  • Always check that there is no power on hybrid and Repeater Board before you disconnect any cable.
  • Always open the clamps of the connector by pressing the two springs at the end of the detector, before inserting a connector into a port.
  • Avoid any lateral forces on the cbales close to the connectors since this easily leads to the retraction of a pin.

-- OlafBehrendt - 08 Feb 2008

Edit | Attach | Watch | Print version | History: r4 < r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r2 - 2008-02-09 - OlafBehrendt
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    LHCb All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2021 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback