The migration will start 21 on Monday. Before Monday we have to do the following:
- 1 We have to do certification test of the new release. The bkk certification data base is updated to the new system. To make a real example I have to ask the Oracle support to copy data from the production data base to the certification data base Action Zoltan(to ask the oracle support, Frederico to make the test(ongoing).
- 2 We have to update the production data base during 16 of Friday. We have to make sure, new request can not be created. Action Zoltan
- 3 We have to migrate the current request from the current system to the new system. It can be start at 17th. Action?
- 4
--
ZoltanMathe - 14-Feb-2011