Sub detector |
Task |
Responsible |
start_DATE |
end_DATE |
Reference |
COMMENTS |
STATUS |
RICH 1 |
Installation of the Lower Photon Funnel on the RICH1 detector |
C. Frei |
02 February 2009 |
06 February 2009 |
RU0003 |
|
done |
Calorimeter |
COMMISSIONING OF ECAL C-SIDE |
I. Machikhiliyan |
02 February 2009 |
06 February 2009 |
CE0010 |
Yellow Nacelle |
done |
PS |
Check of the VFE electronics |
P.Perret |
02 March 2009 |
13 March 2009 |
CP0007 |
|
done |
Outer Tracker |
INSTALL HEATING BLANKETS ON T2-Q02-VX |
A. Pellegrino |
03 February 2009 |
20 February 2009 |
TO0003 |
heating T2-Q02-VX for about 10 days |
done |
PS |
Repair of a broken pin in a PS backplane crate A-side. |
Patrick Robbe |
05 February 2009 |
05 February 2009 |
CP0005 |
|
done |
VELO |
Work on the cooling system close to the VELO |
E. Jans |
05 January 2009 |
16 January 2009 |
TV0001 |
scaffolding |
done |
HCAL |
swap 2 cables of CW/PMT in the central part |
Iouri Guz |
06 February 2009 |
06 February 2009 |
HC0003 |
White nacelle, side A |
done |
RICH 2 |
Check of the gas tighness of the gas enclosure of the RCH2 |
C. Frei |
06 January 2009 |
26 February 2009 |
RD0001 |
|
done |
Beam Pipe |
Beam pipe protection removal/installation for M1 survey |
P. Lepeule |
08 January 2009 |
09 September 2009 |
VX0001 |
Protection back on 9.01 at 17:00 |
done |
Tracker Turicensis |
Work on electronics boxes and opening of TT station for film crew |
J. van Tilburg |
09 February 2009 |
13 February 2009 |
TT0001 |
ongoing |
done |
RICH 1 |
REMOVAL OF THE RICH1 UPPER HPD ARRAY |
B. Cameron |
09 January 2009 |
15 January 2009 |
RU0002 |
Handling |
done |
Infrastructure |
High Fog OT phase 1 |
E. Thomas |
10 August 2009 |
14 August 2009 |
IX004 |
No work between magnet and RICH2 |
done |
PS |
Tuning of LED light pulse hight on PS |
Evgeny GUSHCHIN |
10 February 2009 |
17 February 2009 |
CP0006 |
Green nacelle |
done |
RICH 1 |
Installation of trolley with the HPD array |
B. Cameron |
11 February 2009 |
12 February 2009 |
RU0004 |
|
done |
Inner Tracker |
Install Service Box tilting |
F Blanc |
11 March 2009 |
27 March 2009 |
TI0005 |
|
done |
Magnet |
checking position of coils on supports |
R. Lindner |
12 January 2009 |
16 January 2009 |
MX0001 |
|
done |
Infrastructure |
Scaffolding for RMS measurements |
B. Corajod |
12 January 2009 |
14 January 2009 |
IX0001 |
scaffolding |
done |
Outer Tracker |
Installation of a new access platform close to the magnet which will replace the existing one |
C. Fournier |
12 January 2009 |
06 March 2009 |
TO0001 |
green nacelle |
done |
Calorimeter |
Change of Turbine HCAL side A |
R. Kristic |
13 January 2009 |
13 January 2009 |
CE0001 |
|
done |
Muon |
PERPARATION FOR/AND INSTALLATION OF CHAMBER SUPPORTS, MODIFICATION TO FLEXIBLE GAS PIPES |
B. Schmidt, A. Cardini |
13 January 2009 |
20 February 2009 |
UX0001 |
yellow resp. white nacelle |
done |
Muon |
FINALIZATION OF AIR COOLING STATIONS M2-M5 |
B. Schmdt |
13 January 2009 |
20 February 2009 |
UX0002 |
|
done |
MOEDAL |
Preparation work |
D. Lacarrere, R. Soluk |
13 May 2009 |
15 May 2009 |
DD0001 |
|
done |
RICH 2 |
CLOSURE OF THE GAS ENCLOSURE |
C. Frei |
14 August 2009 |
14 August 2009 |
|
|
done |
Inner Tracker |
Repair VCSELs on digitizer boards |
F. Blanc |
15 April 2009 |
24 April 2009 |
|
|
done |
RICH 1 |
Installation of the Upper Photon Funnel |
Christoph Frei |
16 February 2009 |
25 February 2009 |
RU0005 |
Green Nacelle |
done |
ECAL |
INSTALLATION OF HV-BOXES ON A-SIDE |
Irina Machikhiliyan |
16 February 2009 |
20 February 2009 |
CE0011 |
|
done |
Muon |
M1 CHAMBER INSTALLATION |
B. Schmidt, A. Cardini |
16 February 2009 |
20 June 2009 |
PPSPS-M1-Chamber-Installation |
http://lhcb-tech-coor.web.cern.ch/lhcb-tech-coor/Task_description/M1_closing.wmv |
done |
Inner Tracker |
TEST SERVICE BOXES ON IT-1C AND IT-3C |
F. Blanc |
16 January 2009 |
20 January 2009 |
TI0001 |
|
done |
Calorimeter |
Access to HCAL/C to commission CW/PMT |
Iouri Guz |
16 January 2009 |
20 January 2009 |
CE0002 |
yello nacelle |
done |
Infrastructure |
Dismount top level of RICH 2 tower side A |
C. Fournier |
16 March 2009 |
18 March 2009 |
IX0004 |
During operation, OT/IT/M1/PS/SPD closed |
done |
Muon |
INSTALLATION OF LONG ALIGNMENT BARS FOR STATION M1 |
B. Schmidt, Th. Schneider |
17 February 2009 |
02 Mars 2009 |
UX0004 |
yellow nacelle |
done |
SPD |
CALO BROKEN CONTROL/CLOCK CABLE |
Eduardo Picatoste Olloqui |
17 March 2009 |
20 March 2009 |
CP0010 |
|
done |
RICH 2 |
Replacement of HPD side C |
C. Frei |
18 March 2009 |
25 March 2009 |
RD0003 |
M1 & Calo closed on that side |
done |
ECAL |
Opening ECAL A-side |
Robert Kristic |
19 June 2009 |
19 June 2009 |
CE0017 |
|
done |
ECAL |
Install modified integrators on ECAL A-side |
Irina Machikhiliyan |
19 June 2009 |
22 June 2009 |
CE0018 |
|
done |
ECAL |
INSTALLATION OF INTEGRATORS, ECAL C-SIDE |
Irina Machikhiliyan |
2 July 2009 |
6 July 2009 |
CE0019 |
|
done |
RICH 1 |
Photon Funnel, dismount |
C. Frei |
20 January 2009 |
30 January 2009 |
RU0001 |
|
done |
Inner Tracker |
SERVICE BOX TILTING MECHANISM (IT-2A) |
F. Blanc |
20 January 2009 |
21 January 2009 |
TI0002 |
|
done |
Calorimeter |
ECAL INSTALLATION OF HV-BOXES ON C-SIDE |
Irina Machikhiliyan |
20 January 2009 |
23 January 2009 |
CE0003 |
|
done |
ECAL |
Replacement of malfunctioning PMT/C-W doublets |
Irina Machikhiliyan |
2009-08-18 |
2009-08-19 |
CE0020 |
|
done |
ECAL |
Replacement of one fuse in LV chain (A-side) and two cable connectors (C and A side) |
Irina Machikhiliyan |
2009-09-04 |
2009-09-04 |
CE0021 |
|
done |
MOEDAL |
Put up a few test panels and drill holes on top of VELO |
Richard SOLUK |
2009-09-14 |
2009-09-16 |
DD0002 |
|
done |
ECAL |
MAINTENANCE OF ECAL VOLTAGE DISTRIBUTION/LED TRIGGER SYSTEMS |
Irina Machikhiliyan |
2009-09-29 |
2009-09-30 |
CE0022 |
|
in preparation |
ECAL |
Repair the ECAL HV_control |
Anatoly Konoplyannikov |
2009-10-05 |
2009-10-05 |
CE0023 |
|
done |
RICH 2 |
Replacement of HPD side A |
C. Frei |
2009-10-07 |
2009-10-09 |
|
M1 & Calo closed on that side. |
in preparation |
RICH 2 |
Replacement of HPD side C |
C. Frei |
2009-10-14 |
2009-10-19 |
|
M1 & Calo closed on that side. |
in preparation |
Calorimeter |
Access to HCAL/C to commission CW/PMT |
Iouri Guz |
21 January 2009 |
26 January 2009 |
CE0004 |
|
done |
Calorimeter |
TUNING OF LED SYSTEM |
Evgeny Gushchin |
21 January 2009 |
09 February 2009 |
CE0008 |
Green nacelle, ECAL platform & RCH 2 tower |
done |
Calorimeter |
Closing of CALO A-side for M1 |
R. Kristic |
22 April 2009 |
22 April 2009 |
CE00016 |
at 13:00 |
done |
Calorimeter |
Check of the PS VFE electronics |
P.Perret |
22 January 2009 |
06 February 2009 |
CE0005 |
|
done |
Calorimeter |
Work on Calorimeter front-end electronics |
Frédéric Machefert |
22 January 2009 |
22 January 2009 |
CE0007 |
Work on Calo platform |
done |
HCAL |
REPLACEMENT RADSOURCE CASSETTE |
R. Dzhelyadin |
22 May 2009 |
22 May 2009 |
HC0004 |
~ 3h |
done |
Inner Tracker |
SERVICE BOXES ON IT-1A,2A,3A |
F. Blanc |
23 January 2009 |
27 January 2009 |
TI0003 |
|
done |
Muon |
Replacement of some chambers of Muon stations M2-M5 |
B. Schmidt |
23 March 2009 |
30 April 2009 |
UX0005 |
|
started |
VELO |
Maintenance of the three turbo pumps |
E. Jans |
24 March 2009 |
26 March 2009 |
TV0002 |
|
done |
RICH 1 |
HPD array to the detector C-side |
B. Cameron |
25 February 2009 |
26 February 2009 |
RU0006 |
|
done |
Inner Tracker |
Repair electronics on IT-2A |
F. Blanc |
25 February 2009 |
27 February 2009 |
TI0004 |
|
done |
RICH 2 |
Replacement of HPD side A |
C. Frei |
25 March 2009 |
1 April 2009 |
RD0003 |
M1 & Calo closed on that side |
done |
ECAL |
ECAL HV CONTROL BOARD REPLACEMENT |
A. Konoplyannikov |
25 March 2009 |
25 March 2009 |
CE0014 |
|
done |
Magnet |
EPDM insertion between upstream coil support and coil |
C. Fournier |
25 May 2009 |
29 May 2009 |
MX0002 |
|
done |
ECAL |
Opening A-side; Beginning of CALO access A-side |
R. Kristic |
26 February 2009 |
02 March 2009 |
CE0012 |
green nacelle in center |
done |
SPD |
Cable extension for a control clock cable of the SPD |
Eduardo Picatoste Olloqui |
26 February 2009 |
27 February 2009 |
CP0008 |
|
done |
PS/SPD |
TUNING OF PS/SPD LED SYSTEM |
E. GUSHCHIN |
26 February 2009 |
15 March 2009 |
CP0009 |
|
done |
Outer Tracker |
INSTALL CTRLBOX PLATFORMS C-SIDE |
A. Pellegrino |
26 January 2009 |
30 January 2009 |
TO0002 |
|
done |
Calorimeter |
The installation of PMT/C-W |
I. Machikhiliyan |
26 January 2009 |
06 February 2009 |
CE0006 |
yellow nacelle |
done |
Infrastructure |
Bunker extension access on side C and A |
C. Fournier |
26 January 2009 |
14 February 2009 |
IX0002 |
Access on bunker extension restricted |
done |
Muon |
PERPARATION/MODIFICATION OF CALBING FOR CHAMBERS OF REGION R1 AND R2 |
B. Schmidt, A. Cardini |
26 January 2009 |
24 Mars 2009 |
UX0003 |
|
done |
PS |
Change of the PS VFE LV patch panels |
Pascal PERRET |
26 June 2009 |
6 July 2009 |
CP0012 |
|
done |
RICH 1 |
OPENING THE GAS ENCLOSURE FOR SURVEY AND REPAIRS. |
B. Cameron |
26 March 2009 |
27 March 2009 |
RU0007 |
|
done |
Calorimeter |
The installation of PMT/C-W |
Irina Machikhiliyan |
27 February 2009 |
13 March 2009 |
CE0013 |
|
done |
RICH 2 |
Installation of the LAMS |
Didier Piedigrossi |
27 February 2009 |
6 March 2009 |
RD0002 |
|
done |
Calorimeter |
CALO SPD VFE 2 REPAIR |
E. P. Olloqui |
27 January 2009 |
30 January 2009 |
CE0009 |
M1 closed on C-side |
done |
Infrastructure |
Installation of access under balcony |
C. Fournier |
28 April 2009 |
29 May 2009 |
IX0005 |
|
done |
Infrastructure |
ABSOLUTE GRAVITY MEASUREMENTS |
S. Guillaume |
29 June 2009 |
30 June 2009 |
IX0006 |
UX85A, close to PZ |
done |
Tracker Turicensis |
Exchange TT modules and work on service boxes |
Jeroen van Tilburg |
29 June 2015 |
03 July 2009 |
TT0002 |
|
in preparation |
SPD |
CALO SPD CONTROL CABLE REPARATION |
P. Perret |
3 June 2009 |
4 June 2009 |
CP0011 |
needed vertical nacelle |
done |
ECAL |
DISMOUNTING OF INTEGRATORS, ECAL C-SIDE |
I. Machikhiliyan |
6 April 2009 |
20 April 2009 |
CE00015 |
2h access |
done |
Inner Tracker |
Repair cables in RMS patch panel |
F. Blanc |
6 August 2009 |
13 August 2009 |
IT0007 |
|
done |
VELO |
- Changing pressure and temperature sensors |
Eddy Jans |
6 July 2009 |
10 July 2009 |
TV0003 |
|
done |
Infrastructure |
Dismount 2nd level of RICH 2 tower side C |
C. Fournier |
9 March 2009 |
11 March 2009 |
IX0003 |
|
done |
|
template |
|
|
|
TEMPLATE |
|
in preparation |