TASK |
DATE |
COMMENTS |
STATUS |
SG8 cooling regulation for RICH1 |
09/2009 (TBC) |
First proposal received from CV |
|
Cooling Towers maintenance |
weeks 18 to 20 |
Detailed schedule and cooling power availibility |
Done |
Cooling DSS Flowswitches Change |
during Cooling Shutdown |
FS(low flow) for Muon A and C sides, Balcony, D3a -- Diff pressure sensors for UXA~C Mixed and Chilled? water |
Done |
Detector cooling repair |
21/11/08 |
Repair and clean flow meters, fix pneumatic leak, change PLC UPS, Change Backup chiller pump |
Done |
Detector cooling annual maintenance |
week 18 to 20 |
|
Done |
Gas systems maintenance |
25/11 to 28/02 |
Up-to-date schedule |
Done |
Access System maintenance |
2-6/03 |
Includes Mobile plugs. Access problem limited to UXB on 09/3 Schedule and Impact |
Done |
18 kV transformers conformity work |
Week 19 (7-8/05) |
Agreed with TS/EL |
Done |
18 kV transformers triennial maintenance |
Week 19 (7-8/05) |
Agreed with TS/EL |
Done |
18kV transformers coupling switch |
|
Offer from TS/EL. Rejected. |
|
Mixed/Chilled water sand filters |
Week 26 |
Washing water recycling work remaining |
Done |
Mixed water Standalone unit |
Week 18 |
DAI issued |
Done |
Standalone cooling plants (Online, SG) maintenance |
15-16/12/2008 |
Offer received. |
Done |
Ventillation - Shielding against air from the tunnel |
|
|
Ongoing since week 18 |
EXD/EOD UPS ventillation |
|
Blowers to install |
|
Gas supply: C4F10 pipe heating blankets |
|
Need to be checked / refurbished |
|
Gas supply monitoring |
|
|
|
Lifting Equipments control |
10/02 - 12/02 |
All lifting tools concerned See list in logbook |
Done |
UPS UX85 maintenance |
19/2/2009 |
Report available |
Done |
UPS UX85 pieces replacment |
No date yet |
Anticipation of 2010 replacements (batteries and other components will reach end of life in 2010) |
|
Refurbishment of Machine Safe Power for TFC |
06/2009 |
Including AUL |
Done |
TASK |
DATE |
COMMENTS |
STATUS |
Intercom XCR |
Week 34 |
Safe Communication with FB CCC |
Done |
SNIFFER IS37 |
9/02 to 13/02 |
System off during day, operational in the evening |
Done |
Evacuation sirens test |
1h, to be scheduled (1-5/12/08?) |
Cavern to be evacuated |
Canceled |
Hi-Fog / Marioff |
4/12/08 |
Date confirmed by CMS. Report EDMS 980670 |
Done |
Hi-Fog / Marioff |
15/09/09 |
2009-2010 Maintenance |
|
AUG layout refurbishment and installation |
Completed week 35 |
|
Done |
AUG tests |
07/05/2009 |
Morning underground afternoon surface. Pit closed |
Done |
DSS Maintenance and tests |
07-08/05/2009 |
|
Done |
Biometry PZ85 |
11/12/2008 |
Will be activated when final set of bypass padlock and keys will come |
Done |
Biometry by-pass PZ and UX |
14/11/08 Reception 17/11/08 |
Padlocks must be changed (final closure plan) |
Done |
MAD key in XCR Padlock must be changed |
14/11/08 Reception 17/11/08 |
Padlocks must be changed (final closure plan) |
Done |
Flammable gas IS37 reception |
11/12/2008 - 22/01/09 |
Reception 11/12/08 and 22/01/09 waiting for report from SC |
Done |
CO2 (rack) system Test |
09/01 and 23/01 |
Full test wit SC waiting for report from SC |
Done |
ODH maintenance and IS37 yearly tests |
09/02 to 13/02 |
Sirens and Flash light done during Xmas |
Done |
Red Phones IS37 |
|
Request done to TS/ASE |
ongoing |
Smoke UX85 maintenance and IS37 yearly test |
16/2 to 20/2 |
|
Done |
Smoke Racks UX85 maintenance |
02/2 to 06/2 |
|
Done |
Sump pump IS37 |
Week 18-20 |
Need confirmation from EN/CV |
Done |
Evacuation IS37 test and maintenance + ODH link |
Xmas period |
30/12/2008 |
Done |
Evac button in XCR |
|
Following task force recommendation |
Done |
OT Sprinkler system |
Week 33 and Week 41 |
First part completed |
|
SX8 labs evacuation Tower |
2009 |
Start week 9 |
Done |