-- RolfLindner - 2009-09-07

Site activities

General support

Location Type Task Responsible end_DATE COMMENTS STATUS
UXB Access RICH 2 tower Cedric, Patrick (ALTEAD) 15 September 2009 1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 big grin done
SX8 Infrastructure Labo installation 2nd floor Bernard Ch. 2009-09-11   big grin done
UXB Access Scaffolding Moedal Bernard&Berni&Patrick 2009-09-14   big grin done
SX8 Infrastructure Electricity 1st floor Berni 2009-09-18 97% Network OK and temporary lighting available smile started
UXB Detector Remove RICH 1 scintillator Bernard & Berni 2009-09-14 Waiting for HV to be disconnected big grin done
3894 Public Relation Poster Bernard 2009-09-07   big grin done
3894 Infrastructure Screen and plug bars Berni 2009-09-11   big grin done
3894 Access Veranda Bernard 2009-09-25 waiting for offer smile started
UXB Detector ARMS cable: MF4, Calo Laurent, Rolf 2009-09-16   big grin done
UXA Access structure on crane Berni 2009-09-11 to be inspected afterwards big grin done
UXB Access remove scaffolding for MoEdal B & B and Patrick 2009-09-16 as soon as possible big grin done
UXB Detector prepare blocks for RICH 1 crane rail Bernard Ch 2009-10-8   big grin done
Underground Maintenance Mixed water filter Bernard Co 2009-09-30 B1 remains to be done big grin done
Underground Detector Survey of RICH 2 superstructure Cedric 2009-09-16 together with JCG big grin done
UXB Detector Survey of M1 Cedric 2009-09-16 together with JCG big grin done
Underground Maintenance Repair of pneumatic pipes Berni 2009-09-23 B1 Muon A+C and Balcony remain to be done big grin done
UXB Detector Dismount OT scintillator support Cedric 2009-10-01   big grin done
UXB Detector Fixation of SAMs Gerard 2009-10-09   big grin done
UXB Access Installation of Platforms RICH 1 side A Gerard 2009-10-08   big grin done
SX8 Refurbishment Follow up of electricity in common lab Berni 2009-10-30 Waiting for raacks (to come week 48) smile started
UXB Detector Follow up of connectors on ARMs cables Laurent 2009-10-09   big grin done
Underground Infrastructure Electrical power for RICH Systems on Balcony (cables from UX85 A to B) Laurent 2009-10-09 Nacelle in UX on 28-29/11 big grin done
Underground Civil Engineering Cutting plates in UGX Cosmi 2009-10-07   big grin done
Surface Infrastructure Modifications to staircase daniel 2009-10-09   big grin done
SX8 Infrastructure Emergency doors daniel 2009-10-07 Round handle to be installed outside smile started
SX8 Refurbishment Stairs - Metallic sheets daniel 2009-10-09   big grin done
SX8 Refurbishment Painting structure daniel 2009-10-16   big grin done
UXA Infrastructure Workshops for radio. components daniel 2009-10-30   smile started
UXB Infrastructure Painting ground daniel 2009-11-06 Start on 02/11 big grin done
UXA Infrastructure Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) Laurent 2009-10-12   big grin done
UXA Infrastructure Test System ARMS complet Laurent 2009-10-16 Two labels missing (contact Rolf) smile started
Surface Access Install cable SX8-Labo 2eme etage pour Syst.Acces Laurent 2009-10-16   big grin done
UXB Infrastructure Alim sur D4+Ethernet pour Camera caverne Laurent 2009-10-23 50% done (alim D4) smile started
UXB Maintenance leak magnet cooling Berni+ Patrick & Co 2009-10-27 scaffolding needed big grin done
UXB Access RICH 2 tower modif. Cedric 2009-10-30 Waiting for rough material. Cedric will provide an estimate of the delay. roll eyes (sarcastic) in preparation
3894 Refurbishment 3 Screens in conference room Gerard (+ Berni for cable) 2009-10-23 Waiting for material. 90% done big grin done
UXB Infrastructure control of RICH 1 crane dism. Berni+ Patrick & Co 2009-10-30   big grin done
UXB Detector BCAM reference points Cedric 2009-10-23   big grin done
UXA Infrastructure Flexible connection for the pressure measurement Berni 2009-10-23 UXB before Nov 7. UXA before Nov 14 big grin done
SX8 Public Relation Staircase Olivier Callot Berni 2009-10-30   big grin done
UXB Civil Engineering Pumping and cleaning UGC Daniel / Vallier 2009-10-28   big grin done
SX8 Access Common Lab, access to roof, crane, fire detection and balustarde Bernard + Daniel 2009-11-02   smile started
SX8 Access Macrelon plate on balustrade Bernard 2009-11-02 Material arriving. Cosmi will install. Expected for week 49 roll eyes (sarcastic) in preparation
SX8 Refurbishment Stairs to common lab Bernard 2009-10-26   smile started
UXB Infrastructure Water mist- DSS cabling Laurent 2009-11-06   big grin done
UXB Detector Lights-Muon (install protections for tubes) Daniel 2009-11-02 OK for Muon big grin done
UXB Detector Moedal detector installation Daniel 2009-11-05   big grin done
UXB Detector Fixation of 2 additional SAMs (gantry + water mist Gerard 2009-11-09 missing label big grin done
SX8 Refurbishment New lab: reinstallation of pnone lines Berni 2009-11-09   smile started
SX8 Infrastructure Cooling pipes installation in common lab Berni + Levrier 2009-11-16 Ongoing, 50% big grin done
UXB Infrastructure Telex shielding wall for Webcam Gerard 2009-11-09 After work below completed big grin done
SX8 Infrastructure New lab - Detection Incendie Bernard 2009-11-23    
SX8 Infrastructure Barrettes de prises supplementaires+raccordement nouveau UPS online Laurent 2009-11-20 50% (UPS still to be connected) smile started
SX8 Access 2eme cable a installer pour system d'acces Labo 2eme etage Laurent 2009-12-04   big grin done
SG8 Infrastructure Connection direct Centrale detection->EXD Laurent 2009-11-20   smile started
UXA Infrastructure Connection 3 cables HV Muon a DSS + cable AUG Laurent 2009-11-20   roll eyes (sarcastic) in preparation
UXA Infrastructure Connection PLC EL-Borniers-cables pour remonter info sur synoptique surface Laurent 2009-11-27   smile started
UXB Detector Resoudre probleme de lecture Muon Turbines Laurent 2009-11-27   roll eyes (sarcastic) in preparation
156 Detector Arrange storage for Sub detectors All 2009-11-28   smile started

-- RolfLindner - 05 Jan 2009

Edit | Attach | Watch | Print version | History: r16 < r15 < r14 < r13 < r12 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r16 - 2009-11-23 - EricThomas
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    LHCb All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright &© 2008-2023 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback