Location |
Type |
Task |
Responsible |
end_DATE |
COMMENTS |
STATUS |
UXB |
Access |
RICH 2 tower |
Cedric, Patrick (ALTEAD) |
15 September 2009 |
1st level Side A completed: 3-9-09, side C all levels completed: 8-9-09 |
done |
SX8 |
Infrastructure |
Labo installation 2nd floor |
Bernard Ch. |
2009-09-11 |
|
done |
UXB |
Access |
Scaffolding Moedal |
Bernard&Berni&Patrick |
2009-09-14 |
|
done |
SX8 |
Infrastructure |
Electricity 1st floor |
Berni |
2009-09-18 |
97% Network OK and temporary lighting available |
started |
UXB |
Detector |
Remove RICH 1 scintillator |
Bernard & Berni |
2009-09-14 |
Waiting for HV to be disconnected |
done |
3894 |
Public Relation |
Poster |
Bernard |
2009-09-07 |
|
done |
3894 |
Infrastructure |
Screen and plug bars |
Berni |
2009-09-11 |
|
done |
3894 |
Access |
Veranda |
Bernard |
2009-09-25 |
waiting for offer |
started |
UXB |
Detector |
ARMS cable: MF4, Calo |
Laurent, Rolf |
2009-09-16 |
|
done |
UXA |
Access |
structure on crane |
Berni |
2009-09-11 |
to be inspected afterwards |
done |
UXB |
Access |
remove scaffolding for MoEdal |
B & B and Patrick |
2009-09-16 |
as soon as possible |
done |
UXB |
Detector |
prepare blocks for RICH 1 crane rail |
Bernard Ch |
2009-10-8 |
|
done |
Underground |
Maintenance |
Mixed water filter |
Bernard Co |
2009-09-30 |
B1 remains to be done |
done |
Underground |
Detector |
Survey of RICH 2 superstructure |
Cedric |
2009-09-16 |
together with JCG |
done |
UXB |
Detector |
Survey of M1 |
Cedric |
2009-09-16 |
together with JCG |
done |
Underground |
Maintenance |
Repair of pneumatic pipes |
Berni |
2009-09-23 |
B1 Muon A+C and Balcony remain to be done |
done |
UXB |
Detector |
Dismount OT scintillator support |
Cedric |
2009-10-01 |
|
done |
UXB |
Detector |
Fixation of SAMs |
Gerard |
2009-10-09 |
|
done |
UXB |
Access |
Installation of Platforms RICH 1 side A |
Gerard |
2009-10-08 |
|
done |
SX8 |
Refurbishment |
Follow up of electricity in common lab |
Berni |
2009-10-30 |
Waiting for raacks (to come week 48) |
started |
UXB |
Detector |
Follow up of connectors on ARMs cables |
Laurent |
2009-10-09 |
|
done |
Underground |
Infrastructure |
Electrical power for RICH Systems on Balcony (cables from UX85 A to B) |
Laurent |
2009-10-09 |
Nacelle in UX on 28-29/11 |
done |
Underground |
Civil Engineering |
Cutting plates in UGX |
Cosmi |
2009-10-07 |
|
done |
Surface |
Infrastructure |
Modifications to staircase |
daniel |
2009-10-09 |
|
done |
SX8 |
Infrastructure |
Emergency doors |
daniel |
2009-10-07 |
Round handle to be installed outside |
started |
SX8 |
Refurbishment |
Stairs - Metallic sheets |
daniel |
2009-10-09 |
|
done |
SX8 |
Refurbishment |
Painting structure |
daniel |
2009-10-16 |
|
done |
UXA |
Infrastructure |
Workshops for radio. components |
daniel |
2009-10-30 |
|
started |
UXB |
Infrastructure |
Painting ground |
daniel |
2009-11-06 |
Start on 02/11 |
done |
UXA |
Infrastructure |
Cables Installation from SX8 to TDM platform + Magnet room (for Emmergency Pannel) |
Laurent |
2009-10-12 |
|
done |
UXA |
Infrastructure |
Test System ARMS complet |
Laurent |
2009-10-16 |
Two labels missing (contact Rolf) |
started |
Surface |
Access |
Install cable SX8-Labo 2eme etage pour Syst.Acces |
Laurent |
2009-10-16 |
|
done |
UXB |
Infrastructure |
Alim sur D4+Ethernet pour Camera caverne |
Laurent |
2009-10-23 |
50% done (alim D4) |
started |
UXB |
Maintenance |
leak magnet cooling |
Berni+ Patrick & Co |
2009-10-27 |
scaffolding needed |
done |
UXB |
Access |
RICH 2 tower modif. |
Cedric |
2009-10-30 |
Waiting for rough material. Cedric will provide an estimate of the delay. |
in preparation |
3894 |
Refurbishment |
3 Screens in conference room |
Gerard (+ Berni for cable) |
2009-10-23 |
Waiting for material. 90% done |
done |
UXB |
Infrastructure |
control of RICH 1 crane dism. |
Berni+ Patrick & Co |
2009-10-30 |
|
done |
UXB |
Detector |
BCAM reference points |
Cedric |
2009-10-23 |
|
done |
UXA |
Infrastructure |
Flexible connection for the pressure measurement |
Berni |
2009-10-23 |
UXB before Nov 7. UXA before Nov 14 |
done |
SX8 |
Public Relation |
Staircase Olivier Callot |
Berni |
2009-10-30 |
|
done |
UXB |
Civil Engineering |
Pumping and cleaning UGC |
Daniel / Vallier |
2009-10-28 |
|
done |
SX8 |
Access |
Common Lab, access to roof, crane, fire detection and balustarde |
Bernard + Daniel |
2009-11-02 |
|
started |
SX8 |
Access |
Macrelon plate on balustrade |
Bernard |
2009-11-02 |
Material arriving. Cosmi will install. Expected for week 49 |
in preparation |
SX8 |
Refurbishment |
Stairs to common lab |
Bernard |
2009-10-26 |
|
started |
UXB |
Infrastructure |
Water mist- DSS cabling |
Laurent |
2009-11-06 |
|
done |
UXB |
Detector |
Lights-Muon (install protections for tubes) |
Daniel |
2009-11-02 |
OK for Muon |
done |
UXB |
Detector |
Moedal detector installation |
Daniel |
2009-11-05 |
|
done |
UXB |
Detector |
Fixation of 2 additional SAMs (gantry + water mist |
Gerard |
2009-11-09 |
missing label |
done |
SX8 |
Refurbishment |
New lab: reinstallation of pnone lines |
Berni |
2009-11-09 |
|
started |
SX8 |
Infrastructure |
Cooling pipes installation in common lab |
Berni + Levrier |
2009-11-16 |
Ongoing, 50% |
done |
UXB |
Infrastructure |
Telex shielding wall for Webcam |
Gerard |
2009-11-09 |
After work below completed |
done |
SX8 |
Infrastructure |
New lab - Detection Incendie |
Bernard |
2009-11-23 |
|
|
SX8 |
Infrastructure |
Barrettes de prises supplementaires+raccordement nouveau UPS online |
Laurent |
2009-11-20 |
50% (UPS still to be connected) |
started |
SX8 |
Access |
2eme cable a installer pour system d'acces Labo 2eme etage |
Laurent |
2009-12-04 |
|
done |
SG8 |
Infrastructure |
Connection direct Centrale detection->EXD |
Laurent |
2009-11-20 |
|
started |
UXA |
Infrastructure |
Connection 3 cables HV Muon a DSS + cable AUG |
Laurent |
2009-11-20 |
|
in preparation |
UXA |
Infrastructure |
Connection PLC EL-Borniers-cables pour remonter info sur synoptique surface |
Laurent |
2009-11-27 |
|
started |
UXB |
Detector |
Resoudre probleme de lecture Muon Turbines |
Laurent |
2009-11-27 |
|
in preparation |
156 |
Detector |
Arrange storage for Sub detectors |
All |
2009-11-28 |
|
started |