Project Number |
Task |
Contact |
Documents |
Comments |
Status |
Priority |
LHCb_SA10_001 |
Demolition 2889 |
Bernard Corajod |
LHCb_SA10_001 |
Dismantling achieved in March 2010 as expected. |
done |
|
LHCb_SA10_002 |
Preparation of new area (2889) |
Bernard, daniel |
LHCb_SA10_02a LHCb_SA10_02b-sketch LHCb_SA10_02c-planning LHCb_SA10_02d LHCb_SA10_02e LHCb_SA10_02f LHCb_SA10_02g LHCb_SA11_02h |
Purchase of new modules. ALGECO modules (2) installed in May 2011. Installtion of kitchen ongoing (June 2011). |
done |
Start 17 July; Goudronnage is done. Installatio new modules expected for April 2011. Modules installed in May 2011. Kitchen expected for June-July 2011. |
LHCb_SA10_003 |
Preparation of new area in fromt of SG8 |
Bernard, daniel |
LHCb_SA10_003 LHCb_SA10_03a LHCb_SA10_03b LHCb_SA10_003c LHCb_SA10_003d |
Sketch agreed. Work achieved. |
done |
Marks are missing only.Marking scheduled end Sept.2010. Work achieved 10 February 2011. |
LHCb_SA10_004 |
Define sub-detector areas in 156 |
Gerard Decreuse |
LHCb_SA10_004a |
|
done |
|
LHCb_SA10_005 |
Rearrange area in 156 |
Gerard Decreuse |
LHCb_SA10_005a |
Ongoing. |
started |
Start 12/04 |
LHCb_SA10_006 |
Drawing and order of new workshop in SX8 |
Cédric Fournier |
LHCb_SA10_006a LHCb_SA10_006b |
|
done |
installation scheduled the 14th of March 2011 |
LHCb_SA10_007 |
Noise protection offices 1st floor |
Daniel Lacarrere |
LHCb_SA10_007a LHCb_SA10_007b |
ACHIEVED MARCH 2011 |
done |
Delayed - Oct.2010. END March 2011. |
LHCb_SA10_008 |
Improve safety control corner in XCR |
Laurent Roy, Gerard Decreuse |
LHCb_SA10_008a |
Staircases should arrive week 25 |
done |
End of May. Instal during Tech stop |
LHCb_SA10_009 |
Replace pneumatic lines UX85 A/B Gas to be done as well |
Laurent Roy, Cedric Fournier, Daniel Lacarrere |
LHCb_SA10_009a |
All done, still one valve to be changed |
done |
Also gaz to be connected |
LHCb_SA10_010 |
Improve LHCb exhibition, SX |
Daniel Lacarrere, Bernard Chadaj |
LHCb_SA11_010 |
Re-organisation started |
done |
Improvements ongoing |
LHCb_SA10_011 |
Rearrange area around DELPHI zone |
Bernard Corajod |
|
Started. Material gone. Need cleaning |
started |
No date foreseen. |
LHCb_SA10_012 |
Calo moving control units, cabling |
Daniel Lacarrere, Robert Kristic |
|
|
in preparation |
Trigger Robert again (Daniel) |
LHCb_SA10_013 |
Prepare container for storage; light etc. |
Berni, Cédric, Laurent (electricity) |
LHCb_SA10_013 |
lights ok, storage ok, still material to be put in when removing old workshop |
done |
Week 24-25 |
LHCb_SA10_014 |
Electricity buffer UXA |
Bernard Corajod |
|
Signed |
done |
Urgent. |
LHCb_SA10_015 |
Flexible cooling pipes labo SX |
Bernard Corajod, Gerard Decreuse |
|
Completed |
done |
Filling from 18/05. |
LHCb_SA10_016 |
Modification tour Rich2 |
Cédric Fournier |
LHCb_SA10_016 |
|
done |
|
LHCb_SA10_017 |
Plaquettes pour points de mesures RP |
Cédric Fournier |
|
|
done |
Can be installed in any little shutdown |
LHCb_SA10_018 |
Fabrication des gardes corps bunker du extensions |
Cédric Fournier |
LHCb_SA10_018 |
First safety bar done, will be weld this week(35) |
done |
Should be ready for winter technical stop |
LHCb_SA10_019 |
Improvements of the SY8 building |
Daniel Lacarrère |
100% done |
Lighting, painting, electrical convectors. Almost completed (ceiling) |
done |
High priority. Innauguration party 15/06 |
LHCb_SA10_020 |
Traffic sign - access P8 |
Cédric Fournier |
|
|
done |
End june |
LHCb_SA10_021 |
Fire extinguisher fixation - top gantry |
Bernard Corajod |
|
26-28 April 2010 |
done |
Medium |
LHCb_SA10_022 |
Venting of PZ ups alcove |
Gerard Decreuse - Laurent Roy |
|
plaque macrolon pour porte faite, Gerard s'occupe de faire les supports des ventilateurs pour essais |
done |
to be done before the end of April.Completed: 6 May |
LHCb_SA10_023 |
Dismantling of displays at PZ access |
Gerard + Berni |
|
|
done |
en cours |
LHCb_SA10_024 |
catalogue equipement |
Cédric |
LHCb_SA10_024 |
Voir avec Eric pour liens catalogue |
in preparation |
|
LHCb_SA10_025 |
'Outside building' BDG 2869 - roofing |
daniel |
LHCb_SA10_025 LHCb_SA10_025a LHCb_SA10_025b |
Sketch done (Daniel). Waiting for GS |
done |
Started: 1st Phase ; roof achieved 6 August; Phase 2 scheduled for Sept-Oct. |
LHCb_SA10_026 |
Rad Lab PZ85 - windows - floor |
daniel |
LHCb_SA10_026 |
Windows done, Painting of groundm completed |
done |
Finishing works achieved. Available from June 2010 - rest = installation of racks & tables (see Gloria) |
LHCb_SA10_026 |
Tooling for Shielding wall dismantling |
daniel - Patrick -Yann |
LHCb_SA10_026a |
Money allocated. Design finished. Tendering: septembre |
done |
|
LHCb_SA10_027 |
Entrance door to SZ to be fixed |
daniel, Berni |
|
Ongoing |
done |
|
LHCb_SA10_028 |
DSS: Connection HV Muon Interlock, Test prochain technical Stop |
Laurent |
|
|
done |
a faire avant 28 mai |
LHCb_SA10_029 |
Mise en place maintenance 3 UPS 'Online' |
Laurent |
|
Problem with Force10 power supplies in D2 solved. Document for maintenance done. |
done |
Forece10 UPS needs monitoring (Iwanski contacted) https://edms.cern.ch/document/1083288/1 |
LHCb_SA10_030 |
Gestion Tell1 Spare / Modif Base de donnees |
Laurent |
|
tableau Excel Guido mis a jour. Procedure for Exchange on EDMS. Logbook for 'common spare' in place. |
done |
https://edms.cern.ch/document/1083357 |
LHCb_SA10_031 |
Finaliser Doc. 'Panneau Urgence', materiel spare, modif bouton acquit |
Laurent |
|
Doc. a voir avec Nicolas. Button in place |
started |
Bouton fait. |
LHCb_SA10_032 |
PC Niko inside PUS rack UXB |
Gerard |
|
31May-2 June |
done |
|
LHCb_SA10_033 |
RP classification plates: improve fixation |
Cédric |
|
Finally done by Berni |
done |
|
LHCb_SA10_034 |
SX8 - Fencing switcboard area (behind labs) |
Daniel |
LHCb_SA10_034 |
Achieved as scheduled |
done |
High priority |
LHCb_SA10_035 |
Pneumatic back-up by N2. One way valve + flow meter |
Berni |
|
ready |
done |
1/2 day during tech stop |
LHCb_SA10_036 |
TNT par satellite |
Cédric |
|
not on the right stallite, but TNT ok... |
done |
really urgent |
LHCb_SA10_037 |
SX8 - Replacement of ladder |
Daniel |
LHCb_SA10_037 |
Achieved 14-17 June 2010 |
done |
work in background |
LHCb_SA10_038 |
POINT 8 - Entrance - Repair of rail |
Daniel |
LHCb_SA10_038 |
Achieved 14 June 2010 |
done |
work in background |
LHCb_SA10_039 |
SG8 - Painting doors & Updating Safety stickers |
Daniel |
LHCb_SA10_039 |
Scheduled for Sept. 2010 |
done |
work in background |
LHCb_SA10_040 |
SZ8 - Improvements (door & painting) |
Daniel |
LHCb_SA10_040 |
Scheduled for Sept. 2010 |
in preparation |
work in background |
LHCb_SA10_041 |
SX8 - Modif. to a ventil. duct |
Daniel |
LHCb_SA10_041 LHCb_SA10_041a |
Scheduled for Sept. 2010 |
done |
|
LHCb_SA10_042 |
SZ8 - Lighting of LHCb Logo |
daniel |
LHCb_SA10_042 |
Scheduled for March 2010 |
done |
Achieved as scheduled. |
LHCb_SA10_043 |
SX8 - Panel LHCb Control Room |
Daniel |
LHCb_SA10_043 |
Scheduled fro March 2010 |
done |
Achieved as expected. |
LHCb_SA10_044 |
UX85B - Removing of the 100t LASTRA platform |
Sylvain, Patrick, Cédric, daniel |
LHCb_SA10_044 |
Scheduled for next technical stop (30-08 until 02/09) |
done |
Achieved 01/09/2010. Inspection by EN/HM - "boogy" to be replaced ) or declassfication ??? |
LHCb_SA10_045 |
SX8 - Dismantling of 5 storage racks |
Cédric, Patrick, daniel |
|
3 out of 5 dismounted |
done |
Work to be achieved for new access to the WC. |
LHCb_SA10_046 |
Workshop dismantling: sorting of first floor |
Berni, Gerard, Cédric |
|
Progressing well |
done |
|
LHCb_SA10_048 |
Pneumatic Chilled Water D3 |
Berni |
|
|
done |
Tech STop July 19 |
LHCb_SA10_049 |
Stairs Velo |
Cédric, Gérard |
|
installed |
done |
Tech STop December |
LHCb_SA10_050 |
Outside tent: sorting |
Cedric, Patrick, Berni |
|
|
done |
Start to sort the wood |
LHCb_SA10_051 |
DSS Sub detector Documentation/Matrix |
Laurent |
LHCb_SA10_043 |
Velo, Muon, Infrastructure to be update |
started |
60% done |
LHCb_SA10_052 |
Wiener AC/DC converter Monitoring project |
Laurent |
|
definition in progress with Ken |
in preparation |
|
LHCb_SA10_053 |
Screen for XCR and Bat 2 |
Cedric,Gérard |
|
|
done |
Bat.2 should be completed for week 38 |
LHCb_SA10_054 |
platines ancrage levage LASTRA |
Cédric |
LHCb_SA10_054 |
Done by 18th of August |
done |
technical stop end of August |
LHCb_SA10_055 |
Plan escalier acces velo |
Gérard |
LHCb_SA10_055 |
dessin terminé |
done |
|
LHCb_SA10_056 |
VELO - Cooling pipelines - Ice |
Rafael, Cedric,Gerard, Daniel |
LHCb_SA10_56a |
|
done |
Pipelines have been wrapped locally using a very absorbent tissue (3M). |
LHCb_SA10_057 |
Collab. Week diner |
Gerard, Cedric, Patrick |
|
|
done |
|
LHCb_SA10_058 |
Rad workshops - Equipment |
Daniel, Gloria, Cédric |
LHCb_SA10_58a |
old tools to take from the workshop |
done |
Access control done |
LHCb_SA10_060 |
Identification Locaux fermes UX85 |
Daniel |
LHCb_SA10_060a |
Second appointment (GS had no access) |
done |
Work achieved in October 2010. |
LHCb_SA10_061 |
SG8: fill the holes in the wall |
Cédric |
|
|
done |
|
LHCb_SA10_062 |
Extincteurs a deplacer |
Cédric, Daniel |
2 done |
Week 41 |
done |
|
LHCb_SA10_063 |
Fixation Ecran DSU1+tablette clavier (SX8) |
Gerard |
|
|
done |
|
LHCb_SA11_064 |
Banc de mesures magnétiques |
Cédric, Pierre-Ange |
LHCb_SA11_064 |
all material removed |
done |
waiting 01/01/2011 for dismantling of beam pipe protections |
LHCb_SA11_065 |
Installation of multi-tubes for pneumatic applications |
Laurent, Eric, daniel + Momo & Youssouf |
LHCb_SA11_065 LHCb_SA11_065a LHCb_SA11_065b |
pipes in place and still connections (gas) to be done |
done |
Rest connections to gas racks scheduled for 14-18 Feb. 2011. |
LHCb_SA11_066 |
re-installation of H-Cal beam plug after 'incident' |
Cédric, Gérard, Robert |
|
Done by January 25th |
done |
one week |
LHCb_SA11_067 |
Modification Rich2 tower A side |
Cédric, Gérard, Berni, Altead |
|
|
done |
As soon as the HPDs checked |
LHCb_SA11_068 |
fixation of Survey support under TT alu platform |
Cédric |
|
Should be ready for the survey of the magnetic slotted measuring section |
done |
one day(27/01/2011) |
LHCb_SA11_070 |
Barraques ALGECO - Zone LHCb détente |
Bernard, daniel, Eliseo |
LHCb_SA11_070 LHCb_SA11_070a LHCb_SA11_070b LHCb_SA11_070b LHCb_SA11_070c |
Demande d'offres |
done |
Objectif = installation April 2011. Innauguration 01/09 |
LHCb_SA11_071 |
Installation 15 Cables BLS+connectors |
Laurent |
|
Cables in place |
done |
|
LHCb_SA11_072 |
Installation cables RAMSES |
Laurent |
|
3 cables en place. |
done |
|
LHCb_SA11_073 |
Reparation 2 sensors ARMS Muon1, Installation ARMS RICH1 |
Laurent |
|
L'ensemble des capteurs (~30)du systeme ARMS fonctionnent correctement. |
done |
|
LHCb_SA11_074 |
Installation of 3 BLS braquets |
Cédric |
|
I must do that instead of starting welding on bunker |
done |
to be done on February 11th |
LHCb_SA11_075 |
installation of the bunker exstension safety bars |
Cédric |
|
I'll try to prepare the work for monday morning |
done |
to be finished before closing the cavern |
LHCb_SA11_076 |
holes for survey target on magnet |
Cédric |
|
I must do that instead of starting welding on bunker |
done |
1-2hours friday afternoon(11/02/11) |
LHCb_SA11_077 |
grounding of calorimeter tower |
Cédric |
|
thursday 17th of February |
done |
|
LHCb_SA11_078 |
rich compressor vibrations insulation |
Cédric, Gérard |
|
|
done |
March technical stop |
LHCb_SA11_079 |
Construction of the New Mechanical Worshop SX8 |
Cédric |
LHCb_SA11_079 |
|
done |
started 14 March 2011 pm. |
LHCb_SA11_080 |
LHCb Upgrade - New CPU farm at Pit8 |
daniel, Niko et al. |
LHCb_SA11_80a LHCb_SA11_80b LHCb_SA11_80c LHCb_SA11_80d LHCb_SA11_80e |
|
started |
1st discussion 23 March 2011 |
LHCb_SA11_081 |
Workshop Electrical installation |
Cédric-Alexandre Habert |
LHCb_SA11_081 |
power alimentation thursday, May 5. |
done |
installation will end on wednesday(04/20) |
LHCb_SA11_082 |
workshop pneumatiques lignes installation |
Cédric-Gilles Morard |
|
3/4 days of work |
done |
Will be completed at the end of week18 |
LHCb_SA11_083 |
Hole or groove for the evacuation of the workshop sink |
Cédric, Daniel-Scrasa |
|
waiting for the drawing by Eliseo |
done |
as soon as possible |
LHCb_SA11_084 |
painting of the workshop floor |
Cédric-Presiozo |
LHCb_SA11_084 |
Re-painting of the Floor |
done |
Untill Wednesday 15th to Friday 17th of June |
LHCb_SA11_085 |
Labo to empty- Building 13-1-034 |
Cédric, Gérard |
|
Stuff for pit 8 allready removed |
done |
Still the room to clean up, probably friday |
LHCb_SA11_086 |
RIA to move |
Cédric-Gilles Morard |
LHCb_SA11_086 |
Work in two times, first step done(RIA removed). |
done |
Completed end of week24 |
LHCb_SA11_087 |
poster a remettre |
Cédric, Gérard |
|
|
done |
Put back on August,Tuesday 6th |
LHCb_SA11_088 |
modifs atelier(cloisons) |
Cédric-Bejean |
LHCb_SA11_088 |
Installation of sandwiches panels start on wednesday 20 of July |
done |
|
LHCb_SA11_089 |
boite defibrilateur |
Cédric-Bernard |
|
pieces de fixation en preparation |
done |
Installé le 11/03/2011 |
LHCb_SA11_090 |
STORAGE TURBINES IN UX85A |
Laurent - danielLHCb_SA11_090 |
LHCb_SA11_090 |
@ racks installed week 16 may 2011. |
done |
Purchase of 2 racks. (FRANKEL) |
LHCb_SA11_091 |
rails to weld on pillar for the new workshop's switch board |
Cédric-Berni |
|
prepared on friday |
done |
should be weld on monday(04/16) |
LHCb_SA11_092 |
evolynx systeme for the workshop |
Cédric-GS |
|
|
started |
week 36 |
LHCb_SA11_093 |
floor of the first level(aluminium plates) |
Cédric-Gérard |
LHCb_SA11_093 |
|
done |
Should start week 21 |
LHCb_SA11_094 |
fire extinguisher to fix on the GANTRY |
Gérard-Cédric |
|
one out of two done |
started |
during the May technical stop |
LHCb_SA11_095 |
Filter(of Muons cooling) on C side to turn down |
Cédric-Gilles Morard |
|
visit on site to prepare work for winter technical stop done with Vincent PITTIN CV) |
in preparation |
Work must be done during the end year technical stop(december 2011) |
LHCb_SA11_096 |
measuring deformation of prestressed beams on top of shielding wall |
Daniel-Cédric-JC |
|
JC Gayde already aware |
in preparation |
No dead line |
LHCb_SA11_097 |
leaking roof SX8 |
Cédric-Joel Cappiot(GTM) |
|
Visite pour intervention jeudi 5 au matin avec nacelle louée par CV(Gilles Morard) |
done |
as soon as possible |
LHCb_SA11_098 |
Tasks during Technical Stop MAY |
Laurent |
LHCb_SA11_098 . Photo_Input_Temp Photo_Output_Temp |
|
done |
finished Thursday 12th May |
LHCb_SA11_099 |
Installation of machinery |
Cédric, Gérard-Altead |
LHCb_SA11_099 |
EDH done |
done |
Won't start before week 25 |
LHCb_SA11_100 |
Connection machines |
Cédric-James Dilwyn Devine |
|
started on monday 22nd |
done |
at least 2 days |
LHCb_SA11_101 |
support flower pots to weld |
Cédric |
|
Weld to be done at building 108 |
done |
will be finished at the end of this week(week 20) |
LHCb_SA11_102 |
Aluminium piece for Daniel |
Gerard-Cédric-Tengyz |
|
still three final stainless pieces to do, Tengiz will do that on week 24(already informed) |
done |
Week 24 |
LHCb_SA11_103 |
door button of the hall(2885)to replace |
Cédric |
|
|
done |
|
LHCb_SA11_104 |
AUG to replace on the workshop wall |
Daniel-Cédric |
|
will be finnaly put on the right pillar of the door |
in preparation |
During a technical stop |
LHCb_SA11_105 |
Door of the workshop to adjust and grooms to fix |
Cédric-Bejean |
|
Done on monday 6th of June |
done |
week 23(6-7/06) |
LHCb_SA11_106 |
Aluminium plates for the cooling plant(UXAC2) |
Cédric-Gérard |
LHCb_SA11_106 |
50% done |
done |
week 23 |
LHCb_SA11_107 |
PVC pieces for led |
Gérard- Cédric-Yuri |
|
asked for doing it at the principle workshop and response wited for monday 30th |
done |
As soon as possible |
LHCb_SA11_108 |
Transfo. Spare in UX85A |
daniel, Eric, Yann, Patrick |
LHCb_SA11_108a LHCb_SA11_108b |
|
started |
Study ongoing |
LHCB_SA11_109 |
Power SZ8: outreach 07/06/2011 |
Laurent |
|
Support pendant tournage film |
done |
|
LHCB_SA11_110 |
End course spacers for E-Cal & H-Cal when beam pipe protection in place |
Cédric-Tengiz |
LHCb_SA11_110a LHCb_SA11_110bLHCb_SA11_110c LHCb_SA11_110d |
drawings quite completed, material ordered |
in preparation |
for end year technical stop |
LHCB_SA11_111 |
painting of the beam pipe protections |
Cédric-Tengiz-Gérard |
|
Finnaly red/white adhesive tape(already ordered) will be used |
in preparation |
before winter technical stop |
LHCB_SA11_112 |
re-installation of the cupboard |
Cédric-Altead |
|
|
done |
June |
LHCB_SA11_113 |
drawing for manufacturing of inox led braket |
Cédric-Daniel |
LHCb_SA11_113 |
|
done |
|
LHCB_SA11_114 |
3 stainless steal brakets for gift |
Daniel-Cédric Tengiz |
LHCb_SA11_114 |
|
done |
week24 |
LHCB_SA11_115 |
SX8 Electrical distribution Consolidation |
Laurent |
LHCb_SA11_115_Aout LHCb_SA11_115_Sep LHCb_SA11_115_Oct |
|
in preparation |
Travaux debut TS Nov |
LHCB_SA11_116 |
beam on top of the workshop opened area |
Cédric-Gérard-Altead |
LHCb_SA11_116 |
Done week 31 |
done |
Should be done before crane load test |
LHCB_SA11_117 |
Ventilation of the workshop |
Cédric-Gilles Morard |
|
|
done |
~September |
LHCB_SA11_118 |
Water(hot/cold) and sink in the workshop |
Cédric-Gilles Morard |
|
Offer around 2900 CHf |
done |
~September |
LHCB_SA11_119 |
LHCb LASTRA PLATFORM (100t) |
daniel, Yann, Patrick |
LHCb_SA11_119 |
|
started |
|
LHCB_SA11_120 |
Etude amelioration disponibilite EOD SX8 |
Laurent |
LHCb_SA11_120 |
|
in preparation |
Echange UPS 2013 |
LHCB_SA11_121 |
CANALISATIONS - CANIVEAU TECH. SX8-SG8 |
Gilles, daniel, Iniziative |
LHCb_SA11_121 |
|
done |
Démarrage en Nov. 2011 |
LHCB_SA11_122 |
SUX8 - INSTALLATION ELECTRICAL EQUIPMENT |
Laurent, daniel, Fred, Patrick, Yann |
LHCb_SA11_122a LHCb_SA11_122b LHCb_SA11_122c LHCb_SA11_122d LHCb_SA11_122e LHCb_SA11_122f LHCb_SA11_122g |
|
done |
Started 01 Oct.2011 |
LHCB_SA11_123 |
SUX8 - ELAGAGE ARBRES - TRANSFOS |
daniel - Genève Espaces Verts |
LHCb_SA11_123a |
|
done |
Done 12 October 2011 am |
LHCB_SA11_124 |
UX85B - Additional Shield behind M5 |
Burkhardt, daniel, Sylvain |
LHCb_SA11_124a |
installation mid-Feb.12 |
done |
Installation scheduled for the next Winter shunt-down. |
LHCB_SA11_125 |
POINT 8 - Small - WORKS |
Tengiz, daniel, Eric, et al. |
LHCb_SA11_125a LHCb_SA11_125b LHCb_SA11_125c LHCb_SA11_125d LHCb_SA11_125e LHCb_SA12_125f LHCb_SA12_125g LHCb_SA12_125h |
|
done |
|
LHCB_SA12_126 |
Pit8 - NEW VISITOR GALLERY IN UX85B |
Daniel, Eric, Olivier |
LHCb_SA12_126a LHCb_SA12_126b |
Construction fall 2012 |
started |
Installation scheduled for March 2013 |
LHCB_SA12_127 |
SX8 - ROOF OF NEW WORKSHOP |
Cedric, daniel |
LHCb_SA12_127a |
|
started |
|
LHCB_SA12_128 |
3893 - REFECTORY - END |
Bernard, daniel |
LHCb_SA12_128a |
|
done |
|
LHCB_SA12_129 |
Projet Scifi |
DECREUSE Gerard |
LHCb_SA12_129 |
|
|
|
LHCB_SA12_130 |
installation systeme d'extraction atelier |
Cédric-Matec Soudure |
LHCb_SA12_130 |
|
done |
20 Mars 2012 |
LHCB_SA12_131 |
connection electrique extraction atelier |
Cédric-EN-EL(Thierry Charvet) |
LHCb_SA12_131 |
|
done |
Mai |
LHCB_SA12_132 |
Tables BBQ+BBQ |
Cédric-Tengiz |
LHCb_SA12_132A,LHCb_SA12_132B, LHCb_SA12_132C, LHCb_SA12_132D, LHCb_SA12_132E, LHCb_SA12_132F, LHCb_SA12_132G |
dernieres tables en cours de montage(bois sur structure alu), cendriers/poubelles a installer en zone BBQ et sur site |
started |
Fin Octobre |
LHCB_SA12_133 |
Extincteurs atelier+plan de securité+pharmacies |
Cédric-HSE Russo |
LHCb_SA12_133A,LHCb_SA12_133B, LHCb_SA12_133C |
Berlinghi doit venir faire l'installation. Code budgetaire donné |
done |
|
LHCB_SA12_134 |
rangement atelier etage |
Cédric-Gerard-Tengiz |
LHCb_SA12_134 |
tri et rangement visserie commencé par Tengiz,etiquetage armoires fait(provisoire), dernieres anciennes armoires vidées, reste plus qu'a reorganiser les nouvelles armoires |
started |
fin 2012 |
LHCB_SA12_135 |
stokage matières |
Cédric-Tengiz |
LHCb_SA12_135 |
Un peu de rangement effectué, peinture en cours et rangement a continuer... |
started |
Novembre |
LHCB_SA12_136 |
Produits chimiques atelier |
Cédric-HSE Gulley |
LHCb_SA12_136A, LHCb_SA12_136B, LHCb_SA12_136C |
Armoire changée et rangée,Pipettes et signaletique+fiches produiits a fournir. |
done |
|
LHCB_SA12_137 |
SMALL WORKS (cont'd)- 2012 |
Tengiz, daniel et al. |
LHCb_SA12_137 |
|
|
|
LHCB_SA12_138 |
WORKS AT SURFACE (PIT8)-2012 |
Antonio, daniel et al. |
LHCb_SA12_138 |
|
|
|
LHCB_SA12_139 |
REARRAGEMENT LHCB STORAGE AREA |
Franck, daniel et al. |
LHCb_SA12_139 |
|
started |
|
LHCB_SA12_140 |
LHCb DISPLAY-SX8-CINEMA BOX |
daniel et al. |
LHCb_SA12_140 |
|
|
|
LHCB_SA12_141 |
Rearrangement and cleaning around PX |
Cédric-Gérard-Franck-Daniel |
LHCb_SA12_141 |
Racks moved behind the PX, wood and goods removed. |
done |
|
LHCB_SA12_142 |
Heating of the workshop |
Cédric-Gilles Morard |
|
connections to hall heating/ventilation |
|
september |
LHCB_SA12_143 |
Online office |
Daniel-Tengiz-Cedric |
LHCb_SA12_143 |
2 modules welded, still 2 to weld, must be sent week 23 for painting |
done |
end of Jun |
LHCB_SA12_144 |
Magnet consolidation |
Cédric-Olivier-Pierro |
|
Tests de friction operationnel, nouvelles matieres en commande |
in preparation |
|
LHCB_SA12_145 |
Platelage lisse Rich1 |
Cédric-olivier-Gerard |
LHCb_SA12_145 |
installation complete terminée |
done |
TS septembre |
LHCB_SA12_146 |
Zonage au 940(stockage echaffaudages) |
Cédric |
LHCb_SA12_146A, LHCb_SA12_146B |
|
done |
Mi-Aout |
LHCB_SA12_147 |
extension toit coffret cuisine |
Daniel-Tengiz |
LHCb_SA12_147A;LHCb_SA12_147B |
|
done |
Debut septembre |
LHCB_SA12_148 |
renovation Rancho |
Daniel-Cédric-Altead |
LHCb_SA12_148A;LHCb_SA12_148B;LHCb_SA12_148C;LHCb_SA12_148D |
Electricité+sol+mur+cuisine rénové |
started |
Fin Janvier |
LHCB_SA12_149 |
coin impression/café |
Cédric |
LHCb_SA12_149A;LHCb_SA12_149B;LHCb_SA12_149C |
top et table commandé |
started |
fin Octobre |
LHCB_SA12_150 |
Pergolas coin BBQ |
Daniel-Cédric-Tengiz |
LHCb_SA12_150A;LHCb_SA12_150B |
prototype fabriqué |
done |
Projet annulé |
LHCB_SA12_151 |
DEPLACEMENT FIREBRIGADE HUT 6880 |
Eliseo, daniel |
LHCb_SA12_151a |
ACHIEVED |
done |
Achieved as scheduled in Sept. 2012 |
LHCB_SA12_152 |
Tests de friction aimant |
Cédric, Pierro, Olivier |
LHCb_SA12_152 |
Systeme de test pret. Trois firmes doivent etre contactée |
started |
Chantier d'installation prévu pour Septembre 2013 |
LHCb_SA13_153 |
INSTALLATION UPS (2x200kVA) SUX8 |
Laurent, daniel, Thierry, Tengiz |
LHCb_SA13_153a |
ACHIEVED |
done |
Achieved in November 2012 |
LHCb_SA13_154 |
INSTALLATION UPS (2x100kVA) UX85A |
Laurent, daniel, Thierry, Tengiz |
LHCb_SA13_154a |
ACHIEVED |
done |
Achievde in Jan.-Feb. 2013 |
LHCb_SA13_155 |
INSTALLATION RACKS (DELL) SX8 (2885 R-007) |
Laurent, daniel, Tengiz, Loîc |
LHCb_SA13_155a |
In preparation |
started |
Installation scheduled for 4-6 March 2013. |
LHCb_SA13_156 |
NEW VISITOR PLATFORM IN UX85B |
Olivier, Cédric, daniel |
LHCb_SA13_156a |
Fabrication launched |
started |
Scheduled for end of March 2013. |
LHCb_SA13_157 |
NEW LHCb BUILDING |
Eliseo, Rolf, Eric, Niko, daniel |
LHCb_SA13_157a |
Preparation Call for Tenders |
started |
Goal = start construction Jan. 2014. |
LHCb_SA13_158 |
PREPARATION OPEN DAY SEPT.2013 |
Bolek, Gloria, Eric, Rolf, daniel |
LHCb_SA13_158a |
PROPOSAL |
in preparation |
Proposal done in Jan. 2013 |
LHCb_SA13_159 |
PREPARATION ROUTES FOR OPTICAL FIBERS |
Niko, Laurent, Ken, daniel |
LHCb_SA13_159a |
Investigations |
in preparation |
Investigations of 2 possible options. |
LHCb_SA13_160 |
ADDITIONAL SHIELD BEHIND MUON 5 |
Robert, Rolf, Burkardt, Olivier, daniel |
|
|
|
|
LHCb_SA13_161 |
MOEDAL INTERVENTIONS - VELO AREA |
Richard, daniel |
|
|
|
|
LHCb_SA13_162 |
REFURBISHMENT OF DELPHI BARREL AREA |
Tengiz, daniel |
|
|
|
|