LHCb LS1 Project
Schedule Overview
- LS1-2013.JPG:
- LS1-2014.JPG:
Browse Schedule Details
Useful information
CV availibility (provisional information)
No demineralized water from 15/5/ to 30/7
Period 1
- HVAC running
- No Demineralized water
- 50% (3-4 weeks in a row) without Mixed and Chilled water in UX85
Period 2
- HVAC running
- No Demineralized water
- 10% without Mixed and Chilled water in UX85
Period 3
- No HVAC (no cooling and no humidity control, heating OK, Ventilation OK)
- No Mixed and Chilled Water
- Mixed and chilled water in UX limited to 300 KW.
Period 4
- HVAC not available 90% - Heating and Ventillation OK
- Mixed Chilled Water not available (90%)
Period 1-4: Sept 2013 - April 2014
- Porvisional mixed water supply: limited to 300 kW
MAINTENANCE 2014
Weeks 48 to 50: from 24/12 to 12/12/2014
Detector Cooling Systems maintenance
- Planning
Beam Pipe Dismantling schedule
- Vacuum chamber dismantling:
Meetings b3894 (P8)
Safety and access:
- All activities are subject to declaration in the IMPACT
system.
- Check your access rights in ADAMS
system
Lift maintenance schedule
Visits
- To schedule a visit to LHCb facilities, follow the instuctions given here
. For assistance please contact LHCb Secretariat
Visits Black-out dates
Visits will be possible until February 13.
- Also check the PZ85 lift maintenance schedule above.
--
EricThomas - 09-Oct-2012