SYSTEM |
item |
milestone |
2014 |
Sept-2015 |
number |
fraction achieved |
integral |
comment |
RICH |
CLARO + Front-End Board |
"EDR 7th of Oct" |
Oct-14 |
Oct-14 |
1 |
1 |
1 |
https://indico.cern.ch/event/344190/ |
RICH |
Elementary Cell |
"EDR 16th of Oct Baseboard+FEB+Backboard mechs + thermal" |
Oct-14 |
Oct-14 |
2 |
1 |
2 |
https://indico.cern.ch/event/344560/ |
MUON |
Spare MWPC |
start production (PRR) |
Feb-15 |
Feb-15 |
3 |
1 |
3 |
24-Feb |
SCIFI |
prototype module |
Large size prototype module (>= 2.5 x 0.54 m2) |
Apr-15 |
Apr-15 |
4 |
1 |
4 |
https://indico.cern.ch/event/406444/ |
CALORIMETER |
Front-End ASIC |
EDR |
Apr-15 |
Apr-15 |
5 |
1 |
5 |
was 24 April |
VELO |
sensors |
Sensor and thinned bump bonding EDR |
Apr-15 |
May-15 |
6 |
1 |
6 |
https://indico.cern.ch/event/396256/timetable/#20150601 |
UPSTREAM TRACKER |
SALT Chip |
SALT EDR |
May-15 |
May-15 |
7 |
1 |
7 |
https://indico.cern.ch/event/394628/ |
UPSTREAM TRACKER |
FLEX cables |
FLEX CABLE EDR |
May-15 |
May-15 |
8 |
1 |
8 |
https://indico.cern.ch/event/394628/ |
UPSTREAM TRACKER |
Staves |
Stave EDR |
May-15 |
May-15 |
9 |
1 |
9 |
https://indico.cern.ch/event/394628/ |
SCIFI |
"Fibres mats modules" |
Joint EDR |
Jun-15 |
Jun-15 |
10 |
1 |
10 |
https://indico.cern.ch/event/406444/ |
UPSTREAM TRACKER |
Sensor |
SENSOR EDR |
Jun-15 |
Jun-15 |
11 |
1 |
11 |
https://indico.cern.ch/event/394628/ |
UPSTREAM TRACKER |
ELECTRONICS |
PEPI/LV EDR |
Jun-15 |
Jun-15 |
12 |
1 |
12 |
https://indico.cern.ch/event/394628/ |
VELO |
electronics |
ASIC EDR |
Jul-15 |
Jul-15 |
13 |
1 |
13 |
|
RICH |
MaPMT |
Place MaPMT order and start production |
Mar-15 |
Oct-15 |
14 |
1 |
14 |
|
VELO |
cooling substrate |
Cooling Substrate EDR |
Jun-15 |
Oct-15 |
15 |
1 |
14 |
|
MUON |
nSYNC |
EDR |
Jun-15 |
Nov-15 |
16 |
1 |
15 |
|
MUON |
nODE |
EDR |
Jun-15 |
Nov-15 |
17 |
1 |
16 |
|
MUON |
nPDM |
EDR |
Jun-15 |
Nov-15 |
18 |
1 |
17 |
|
MUON |
nSB |
EDR |
Jun-15 |
Nov-15 |
19 |
1 |
18 |
|
VELO |
electronics |
hybrid EDR |
Jul-15 |
Nov-15 |
20 |
1 |
19 |
|
VELO |
electronics |
Velopix submission 1 |
Nov-15 |
Nov-15 |
21 |
0 |
0 |
|
RICH |
CLARO + Front-End Board |
PRR |
Jan-15 |
Jan-16 |
22 |
0 |
0 |
|
UPSTREAM TRACKER |
Integration |
Cooling EDR |
Oct-15 |
Jan-16 |
23 |
1 |
20 |
|
DATA PROCESSING |
Trigger |
"1st Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)" |
Feb-16 |
Feb-16 |
24 |
0 |
0 |
|
MUON |
nSYNC |
prototype submission |
Jul-15 |
Feb-16 |
25 |
1 |
21 |
|
RICH |
Elementary Cell |
PRR |
Jan-15 |
Feb-16 |
26 |
0 |
0 |
|
RICH |
RICH1 Mechanics |
"EDR incl Gas encl. Phot boxes Phot funnel Interfaces" |
May-15 |
Feb-16 |
27 |
0 |
0 |
|
RICH |
RICH2 mechanics |
EDR |
Nov-15 |
Feb-16 |
28 |
0 |
0 |
|
UPSTREAM TRACKER |
Sensor |
SENSOR PRR |
Dec-15 |
Feb-16 |
29 |
0 |
0 |
|
UPSTREAM TRACKER |
SALT Chip |
128 ch. ASIC submission |
Jul-15 |
Feb-16 |
30 |
1 |
22 |
|
DATA PROCESSING |
Optical fibres |
Long distance operational reliability |
Feb-16 |
Feb-16 |
31 |
1 |
23 |
|
SCIFI |
"Fibres mats modules" |
Fibre mat PRR |
Jan-16 |
Mar-16 |
32 |
1 |
25 |
|
UPSTREAM TRACKER |
Integration |
UT Box and frame EDR |
Mar-16 |
Mar-16 |
33 |
0 |
0 |
|
MUON |
additional shielding |
EDR |
Oct-15 |
Apr-16 |
34 |
0 |
0 |
|
SCIFI |
SiPM + Electronics + ROB |
Joint EDR |
Dec-15 |
Apr-16 |
35 |
1 |
26 |
|
UPSTREAM TRACKER |
ELECTRONICS |
PEPI/DCB EDR |
Jan-16 |
Apr-16 |
36 |
0 |
0 |
|
DATA PROCESSING |
Event-building |
Event-building with 32-port switch in at least one technology |
Oct-15 |
May-16 |
37 |
1 |
24 |
|
RICH |
Photon Detector Module |
"EDR Optoelectronic chain module + assembly" |
Mar-15 |
May-16 |
38 |
0 |
0 |
|
RICH |
Digital board |
"EDR DB hardware with basic firmware + ECS " |
Jan-15 |
May-16 |
39 |
0 |
0 |
|
SCIFI |
"Fibres mats modules" |
Module PRR |
Mar-16 |
May-16 |
40 |
0 |
0 |
|
UPSTREAM TRACKER |
Sensor |
type A prepr subm. |
Jul-15 |
May-16 |
41 |
0 |
0 |
|
UPSTREAM TRACKER |
Staves |
Instrumented stave PRR |
Feb-16 |
May-16 |
42 |
0 |
0 |
|
VELO |
sensors |
Sensor PRR |
Oct-15 |
May-16 |
43 |
0 |
0 |
|
DATA PROCESSING |
Event-building |
Software scalability 600 nodes |
May-16 |
May-16 |
44 |
0 |
0 |
|
CALORIMETER |
Front-End board (FEB) |
EDR |
Sep-15 |
Jun-16 |
45 |
0 |
0 |
|
CALORIMETER |
Control Board (CB) |
EDR |
Jan-16 |
Jun-16 |
46 |
0 |
0 |
|
CALORIMETER |
"HV Monitoring Calib GBT" |
EDR |
Jan-16 |
Jun-16 |
47 |
0 |
0 |
|
SCIFI |
SiPM + Electronics + ROB |
Cold box and ROB EDR |
Feb-16 |
Jun-16 |
48 |
0 |
0 |
|
UPSTREAM TRACKER |
FLEX cables |
FLEX CABLE PRR |
Jan-16 |
Jun-16 |
49 |
0 |
0 |
|
VELO |
cooling substrate |
Colling Substrate PRR |
Sep-15 |
Jun-16 |
50 |
0 |
0 |
|
MUON |
additional shielding |
launch order (PRR) |
Feb-16 |
Aug-16 |
51 |
0 |
0 |
|
CALORIMETER |
Front-End ASIC |
PRR |
Sep-15 |
Sep-16 |
52 |
0 |
0 |
|
RICH |
RICH1 Mechanics |
PRR |
Oct-15 |
Sep-16 |
53 |
0 |
0 |
|
RICH |
RICH2 mechanics |
PRR |
Jun-16 |
Sep-16 |
54 |
0 |
0 |
|
UPSTREAM TRACKER |
Hybrid |
128 CH HYBRID EDR |
Oct-15 |
Sep-16 |
55 |
0 |
0 |
|
UPSTREAM TRACKER |
SALT Chip |
SALT PRR |
Mar-16 |
Sep-16 |
56 |
0 |
0 |
|
VELO |
electronics |
Velopix Submission 2.1 (final submission) (PRR) |
Apr-16 |
Sep-16 |
57 |
0 |
0 |
|
UPSTREAM TRACKER |
SALT Chip |
SALT production starts |
Oct-16 |
Oct-16 |
58 |
0 |
0 |
|
VELO |
electronics |
"Data cable hybrid OPB PRR" |
Oct-16 |
Oct-16 |
59 |
0 |
0 |
|
CALORIMETER |
Front-End ASIC |
start production |
Nov-16 |
Nov-16 |
60 |
0 |
0 |
|
MUON |
electronics |
Full electronics chain tested |
Jun-16 |
Nov-16 |
61 |
0 |
0 |
|
CALORIMETER |
Front-End board (FEB) |
PRR |
Jan-16 |
Dec-16 |
62 |
0 |
0 |
|
RICH |
Digital board |
PRR |
Aug-15 |
Dec-16 |
63 |
0 |
0 |
|
SCIFI |
Frames |
EDR |
Oct-16 |
Dec-16 |
64 |
0 |
0 |
|
UPSTREAM TRACKER |
Hybrid |
128 CH HYBRID PRR |
May-16 |
Dec-16 |
65 |
0 |
0 |
|
VELO |
detector mechanics |
detector mechanics EDR |
Oct-15 |
Dec-16 |
66 |
0 |
0 |
|
CALORIMETER |
Control Board (CB) |
PRR |
Jul-16 |
Jan-17 |
67 |
0 |
0 |
|
CALORIMETER |
"HV Monitoring Calib GBT" |
PRR |
Jul-16 |
Jan-17 |
68 |
0 |
0 |
|
CALORIMETER |
"HV Monitoring Calib GBT" |
production |
Jan-17 |
Jan-17 |
69 |
0 |
0 |
|
UPSTREAM TRACKER |
Hybrid |
hybrid production starts |
Jan-17 |
Jan-17 |
70 |
0 |
0 |
|
VELO |
module |
Module EDR |
Nov-15 |
Jan-17 |
71 |
0 |
0 |
|
MUON |
nSYNC |
Final submission (PRR) |
Dec-16 |
Mar-17 |
72 |
0 |
0 |
|
MUON |
nODE |
start production (PRR) |
Dec-16 |
Mar-17 |
73 |
0 |
0 |
|
MUON |
nPDM |
start production (PRR) |
Dec-16 |
Mar-17 |
74 |
0 |
0 |
|
MUON |
nSB |
start production (PRR) |
Dec-16 |
Mar-17 |
75 |
0 |
0 |
|
UPSTREAM TRACKER |
FLEX cables |
first batch of cable production completed |
Mar-17 |
Mar-17 |
76 |
0 |
0 |
|
UPSTREAM TRACKER |
ELECTRONICS |
PEPI electronics PRR |
Nov-16 |
Mar-17 |
77 |
0 |
0 |
|
VELO |
RF foil |
RF foil PRR |
Sep-16 |
Mar-17 |
78 |
0 |
0 |
|
VELO |
detector mechanics |
detector mechanics PRR |
Feb-16 |
Mar-17 |
79 |
0 |
0 |
|
SCIFI |
SiPM + Electronics + ROB |
ROB Finish production of components |
Apr-17 |
Apr-17 |
80 |
0 |
0 |
|
SCIFI |
SiPM + Electronics + ROB |
SiPM Series (100%) delivered |
Apr-17 |
Apr-17 |
81 |
0 |
0 |
|
SCIFI |
SiPM + Electronics + ROB |
PACIFIC+electronics PRR |
Sep-16 |
Apr-17 |
82 |
0 |
0 |
|
DATA PROCESSING |
Generic readout board |
10% of boards produced and tested |
Feb-16 |
May-17 |
83 |
0 |
0 |
|
SCIFI |
"Fibres mats modules" |
100% fibres delivered (11'000 km) |
May-17 |
May-17 |
84 |
0 |
0 |
|
DATA PROCESSING |
Farm and Data centre |
Conteiner selected; start construction of data centre building |
May-17 |
May-17 |
85 |
0 |
0 |
|
SCIFI |
Frames |
Assembly zone at P8 available and equipped |
Jun-17 |
Jun-17 |
86 |
0 |
0 |
|
UPSTREAM TRACKER |
FLEX cables |
FLEX cable production completed |
Jul-17 |
Jul-17 |
87 |
0 |
0 |
|
CALORIMETER |
Front-End board (FEB) |
start production |
Aug-17 |
Aug-17 |
88 |
0 |
0 |
|
SCIFI |
"Fibres mats modules" |
100% modules produced |
Aug-17 |
Aug-17 |
89 |
0 |
0 |
|
VELO |
module |
Module PRR |
Jul-16 |
Aug-17 |
90 |
0 |
0 |
|
VELO |
module |
Module production site qualification |
Oct-17 |
Oct-17 |
91 |
0 |
0 |
|
DATA PROCESSING |
Event-building |
"Test in HPC 400 nodes at least 20 Tb/s" |
Oct-17 |
Oct-17 |
92 |
0 |
0 |
|
CALORIMETER |
Control Board (CB) |
start production |
Nov-17 |
Nov-17 |
93 |
0 |
0 |
|
DATA PROCESSING |
Generic readout board |
Production start |
Nov-17 |
Nov-17 |
94 |
0 |
0 |
|
DATA PROCESSING |
Computing |
TDR |
Feb-17 |
Nov-17 |
95 |
0 |
0 |
|
SCIFI |
SiPM + Electronics + ROB |
PACIFIC first production chips available for mounting |
Jan-18 |
Jan-18 |
96 |
0 |
0 |
|
DATA PROCESSING |
Trigger |
"2nd Bi-annual update (CPU growth code performance strategy alternative plateforms review optimisation tasks bandwidth division)" |
Feb-18 |
Feb-18 |
97 |
0 |
0 |
|
VELO |
module |
Module-base integration PRR |
Mar-18 |
Mar-18 |
98 |
0 |
0 |
|
SCIFI |
Frames |
Start module installation on C frames |
Apr-18 |
Apr-18 |
99 |
0 |
0 |
|
UPSTREAM TRACKER |
Hybrid |
hybrid mounting completed |
May-18 |
May-18 |
100 |
0 |
0 |
|
SCIFI |
Frames |
"12 frames mechanics assembled" |
Jun-18 |
Jun-18 |
101 |
0 |
0 |
|
UPSTREAM TRACKER |
Sensor |
sensor production completed |
Jul-18 |
Jul-18 |
102 |
0 |
0 |
|
UPSTREAM TRACKER |
Staves |
1/2 half of instrumented modules ready |
Aug-18 |
Aug-18 |
103 |
0 |
0 |
|
DATA PROCESSING |
Computing |
Computing model for the Run 3 |
Aug-18 |
Aug-18 |
104 |
0 |
0 |
|
DATA PROCESSING |
Farm and Data centre |
Decide on readout network technology |
Sep-18 |
Sep-18 |
105 |
0 |
0 |
|
DATA PROCESSING |
Trigger |
Decision on output bandwidth and on output data flows |
Sep-18 |
Sep-18 |
106 |
0 |
0 |
|
VELO |
module |
Module production complete |
Dec-18 |
Dec-18 |
107 |
0 |
0 |
|
CALORIMETER |
Installation |
ready for installation |
Aug-18 |
Feb-19 |
108 |
0 |
0 |
|
MUON |
Installation |
ready for installation |
Aug-18 |
Feb-19 |
109 |
0 |
0 |
|
UPSTREAM TRACKER |
Staves |
stave instrumentation completed |
Mar-19 |
Mar-19 |
110 |
0 |
0 |
|
RICH |
Installation |
ready for installation |
Aug-18 |
Apr-19 |
111 |
0 |
0 |
|
UPSTREAM TRACKER |
ELECTRONICS |
PEPI electronics completed and ready |
Apr-19 |
Apr-19 |
112 |
0 |
0 |
|
DATA PROCESSING |
Generic readout board |
Production is over |
May-19 |
May-19 |
113 |
0 |
0 |
|
SCIFI |
|
ready for installation |
Aug-18 |
May-19 |
114 |
0 |
0 |
|
UPSTREAM TRACKER |
Installation |
ready for installation |
Jan-19 |
Jun-19 |
115 |
0 |
0 |
|
VELO |
module |
Module-Base integration complete |
Jul-19 |
Jul-19 |
116 |
0 |
0 |
|
DATA PROCESSING |
installation |
Online ready for sub-detectors commissioning |
Jan-19 |
Aug-19 |
117 |
0 |
0 |
|
VELO |
Installation |
ready for installation |
Aug-18 |
Jan-20 |
118 |
0 |
0 |
|
DATA PROCESSING |
Trigger |
Trigger configuration for startup |
Jan-19 |
May-20 |
119 |
0 |
0 |
|
DATA PROCESSING |
Installation |
Online system ready for data-taking |
Jan-20 |
Aug-20 |
120 |
0 |
0 |
|