Work package: Fibre Mats and Module

WP leader: Blake Leverington (b.leverington [at] cern.ch)

WP deputy-leader: Thomas Kirn (kirn [at] physik.rwth-aachen.de)

Scope

The work package deals with the production of Fibre Mats and the construction of Modules which will support the fibre mats, as well as interface to the Read-out Box and Frames.

Relevant Documents

Winding Machine Specifications:

Engineering Design Report: https://cds.cern.ch/record/2004811?ln=en

Production Management Planning & Info: productionplan.docx productionplan.pdf

Brief manual on the production database: DatabaseManual.odt DatabaseManual.pdf

Quality Assurance: QA.pdf

Production

MatWindingCenter

ProductionDatabase: https://scifi.physi.uni-heidelberg.de/db/prod/

Photo Galleries

Current main activities

Production: The production of 1300 2.5m long, 13cm wide, 6-layer fibre mats requires 4 institutes with winding machines producing 4 mats per week. Currently, these winding facilities are being brought into operation such that the Production Readiness reviews can begin in March 2016.

The tooling to build and handle the module is being improved following the Engineering Design Review in July of 2015. Additional modules will be built using the newest production drawings.

Research: Production problems related to bumps of an unacceptable diameter require new techniques to wind a mat that is bump free or undesturbed by these bumps. A mat of wider pitch but more layer was produced as one solution. Another solution which cuts out the bump and splices the 0.25mm fibre back together is also being investigated.

Issues

  • The number of bumps per layer will increase the production time of each mat past the 8-hour limit.

Contributing institutes

  • RWTH Aachen (DE)
  • TU Dortmund (DE)
  • Uni. Heidelberg(DE)
  • Kurchatov Institute (RU) representing
    • Petersburg Nuclear Physics Institute
    • Institute of Theoretical and Experimental Physics
    • Institute for Nuclear Research
    • Institute for High Energy Physics
  • EPFL Lausanne (CH)

Next milestones and reviews

  1. Engineering Meeting to finalize production concepts / decision casting (Thu 15.10.15) Presentation and discussion of this document. Decisions regarding foil or glue casting will be made, as well as other small modifications to the endpiece design.
  2. Order winding wheels (Thu 15.10.15) Every winding center requires three wheels (Six in Russia). Currently an offer from BOMA is being investigated by Dortmund.
  3. Order casting tools (Sun 15.11.15) Glue casting requires 4 jigs per site (8 in Russia).
  4. Order fibres (Sun 15.11.15) 100 km of fibre will be ordered and distributed to the initial winding sites for machine development.
  5. Approve pre‐series (5%) (Mon 15.02.16) 500km of fibre will be ordered and measured to confirm large batch quality.
  6. 50% fibres delivered Thu 15.09.16 Half of the ordered fibres from Kuraray should have arrived at CERN.
  7. Decide on order of NOL fibres (3000 km) Thu 15.12.16 If the NOL fibre provide superior performance to the standard fibres.
  8. Decide on use of 3000 km option Wed 15.02.17 Option in the contract to order fibre beyond what was foreseen to be required.
  9. *100% fibres delivered (11'000 km) Mon 15.05.17 All 11,000km of fibre has been delivered per the supplier contract to CERN.
  10. Start fibre mat production Fri 15.01.16 First winding centre begins production of fibre mats at a reduced pace.
  11. *PRR fibre‐mats Tue 15.03.16 Review of production centres currently in production, schedules and costs.
  12. 10% fibre mats produced Sun 15.05.16
  13. 50% fibre mats produced Thu 15.12.16
  14. *100% fibre mats produced Sat 15.07.17

Further links and material

Production Database: https://scifi.physi.uni-heidelberg.de/db/prod/

OLD:The SciFiDemoModule schedule

OLD: FibreMatTwikiDatabase

-- BlakeLeverington - 18 Jul 2014

*

Topic attachments
I Attachment History Action Size Date Who Comment
Unknown file formatodt DataBaseManual.odt r1 manage 1402.7 K 2016-04-27 - 12:06 SebastianBachmann Short description of the production database (LibreOffice version)
PDFpdf DataBaseManual.pdf r1 manage 1293.0 K 2016-04-27 - 11:57 SebastianBachmann Short description of the production database
PDFpdf QA.pdf r1 manage 10564.2 K 2015-11-06 - 13:40 SebastianBachmann Document on Quality Assurance
PDFpdf main.pdf r1 manage 10564.2 K 2015-11-06 - 13:38 SebastianBachmann Document on Quality Assurance
Unknown file formatdocx productionplan.docx r1 manage 1135.5 K 2015-10-28 - 15:38 BlakeLeverington Production Management
PDFpdf productionplan.pdf r1 manage 1112.8 K 2015-10-28 - 16:53 BlakeLeverington Production Plan pdf
Edit | Attach | Watch | Print version | History: r14 < r13 < r12 < r11 < r10 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r14 - 2018-11-27 - BlakeLeverington
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    LHCb All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2019 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback