All the hardware on this list must be available by June 6
for installation in North Hall prior to testbeam start
- 3 double sided modules - Themis
- 6 complete sets of short kaptons - Themis
- 3 grounding straps - Themis
- 6 sets long kapton cables - Eddy
- 4x6 feed through adaptors - Raymond
- 3 transport boxes - Themis
- 6 fully mounted repeater motherboards - Raymond
- 24 repeater amplifier cards - Jan
- 2 repeater crates (1 supports 5 hybrids) - Raymond
- 6 ECS mezzanines - Lars * Only 8 are mounted. * Total need 6 (TB) + 2 (Assembly) + 1 (Lab 15) = 9 * 1 Mezzanine short
- 6 LV mezzanines - Raymond
- Front panels - Raymond
- 24 data cables - Jan
- 6 control cables - Jan
- TELL1 crate - Paula
- comment 05/05/06 - Delivery expected for 12/05/06
- comment 15/05/06 TELL1 crate delivered to building 15
- 6 TELL1s -
- 24 ARX cards - Jan
- Frontpanels - Raymond
- Interlock box - Jan
- LV - Raymond
- HV - Aldo
- Control Board - Kazu
- 2 pre-series CB mounted, one at CERN and one at the VU needed as production reference.
- 3 prototype CB mounted, not S/W compatible with pre-series.
- Suggest to use prototype CB in assembly and pre-series in TB.
- SPECS Master - Kazu
- SPECS Slave - Kazu
- Temperature Board - Kazu
- Three boards mounted = TB + Assembly + Lab 15
- CAN Master - Kazu
- ELMB - Kazu
- CAN cable Kazu
- Power Supply - Kazu
- ODIN - Richard
- 6U VME crate - Paula
- TTC-tx - Richard
- Optical Splitter - Richard
- Optical fibres - Paula
- GBE board on ODIN - Richard
- Online infrastructure - Artur
- HP switch
- Data Ethernet Cables (1 per TELL1 (6) 24 ideal case)
- Control Ethernet (1 per TELL1 (6 in total) + ODIN)
- Module testing box - Ray
- Manometers/flexible hose to supply nitrogen - Paula
- Scintillator triggers - JC
- Electronics + crates for scintillators - Paula
- Scintillator mechanical support - Ray + ?
- Racks - Paula
- Cable pulling equipment (scaffolding) - Paula
- control room furniture - Paula
- Wireless/Laptop plugs in North Hall - Niko
- Operations PC
- Controls PC
- Login PC at North Area
--
PaulaCollins - 04 May 2006