• Sent to Oxford for Barrel assembly on 2 December 2004.
  • Returned to Cambridge on 20 June 2005.
  • Sent to CERN on 27 July 2005.
  • Returned to Cambridge on 1 March 2007.
  • Sent to CERN on 22 May 2007.
  • Firmware 006/clock hardware fix done.
  • Final QA done on 25 May 2007.
  • Installed in SR1 Test Setup on 6 June 2007.

-- JohnHill - 06 Jun 2007