# Title Dependence Responsible/Operator Week 25 (June 16th)   Week 26 (June 23rd)   Week 27 (June 30th)   Week 28 (July 7th)   Week 29 (July 14th)   Week 29 (July 21st)   Week 30 (July 28th)  
        Target Completed Target Completed Target Completed Target Completed Target Completed Target Completed Target Completed
1 Telescope module planes preparation                                
1.1 Modules selection   Bane, Javier 6/18/2014 no                        
1.2 Modules testing 1.1 Javier     6/25/2014 no                    
1.3 Modules onto handle frame and connection to module adpter cards 1.2 & 3.2 Franck, Maarten, Coralie                 7/14/2014 no        
1.4 Modules tuning and calibration 1.3 Bane, Javier                 7/16/2014 no        
2 Trigger devices preparation                                
2.1 Scinillator fabrication   Franck   yes                        
2.2 Amplifier card for SiPMT production and testing   Yannick         7/1/2014 no                
2.3 Assembly of scintillators to SiPMTs 2.1 Franck, Coralie     6/26/2014 no                    
2.4 Powering and setting up the the counters + scope signals 2.3 Bane             7/7/2014 no            
2.5 Counting tests with RCE 2.4 Bane             7/8/2014 no            
3 Vertical Lab-telescope preparation                                
3.1 Desing of a structure to hold the 6 planes and the SiPMTs for lab cosmic test   Augusto   yes (SiPM not yet)                        
3.2 Prodution of the mechanical structure plus the 6 plane holders and the SiPMTs for lab cosmic test 3.1 Augusto             7/11/2014 no            
3.3 Procurement of the Connectivity set-up   Didier 6/17/2014 yes                        
3.4 Procurement of the Test-bean HSIO adapter card   Bane                            
3.5 Procurement of the needed cables to plug the telescope components for lab cosmic test   Bane         7/3/2014 no                
3.6 Procurement and installation of RCE/HSIO Test-beam software   Bane   partly done?                        
3.7 Procurement and installation of the reconstruction software   Bane, Sergio                            
3.8 Scinillator fabrication 3.2 - 3.6 Bane & all             7/7/2014 no            
3.9 Stages and controller order   Augusto     6/27/2014 no                    
4 Vertical Lab-telescope cosmic data-taking 3.7               7/8/2014 no            
5 Tracking reconstruction validation 3.8               7/9/2014 no            
6 HV-CMOS PCB v5                                
6.1 Design, fabrication and assembly of of boards   Bane 7/18/2014 no                        
6.2 Testing and validation of boards 6.2 Bane 7/19/2014 no                        
6.3 Get wire bonding scheme for this PCB   Bane     7/25/2014 no                    
7 DUT work preparation                                
7.1 Selection of HV-CMOS samples   Daniel                            
7.2 Reception of the FEI4B chips   Daniel                            
7.3 Flip chip gluing of CMOS devices with FE 7.1 & 7.2 Daniel                            
7.4 Gluing and wire bonding to PCB 6.2, 6.3 & 7.3 Gaby, Javier Mesa                            
7.5 Testing and characterization of DUT in the lab 7.4 Daniel, Bane                            
8 DCS and control of the Telscope                                
8.1 Procurement of Windows laptop   Sergio, Yann                            
8.2 ISEG HV crate   Sergio                            
8.3 LV units (if using connectivity set-up PS)   Sergio                            
8.4 DCS: Temperature and humnidity monitoring of DUT box   Javier, Sergio                            
8.5 Control of stages 3.9 Sergio                            
8.6 Cooling system Unistat 705 (Huber)   Sergio                            
9 Telescope sing-off for test-beam                                
9.1 Installation of all the equipment in the lab 1.4, 4, 5, 7.5, 8 Bane, all Unige team                 7/17/2014 no        
9.2 Lab data taking with random/cosmic trigger 9.1 all UniGe team                 7/18/2014 no        
10 Telescope and DUT installation in PS experimental area 9.2                       7/21/2014 no    
11 Data taking and shift period 10                       7/22/2014 no 8/1/2014 no

-- BranislavRistic - 20 Jun 2014

Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r3 - 2014-06-23 - BranislavRistic
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    Main All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2019 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback