The operation configuration is:
  • TTCS Primary Loop is switched ON.
  • The GAC heater is used.
  • The set-point is set to <= 26 C
  • The pump speed is set to 7500 rpm.

Start-up Procedure:

  • Switch On TTCE
  • Set-point to 26 C and switch on GAC
  • Wait until set-point of 26 C is reached.
  • Check sub-cooling:
    • Pt1 > Pt2 + 3C
  • Switch on primary pump with speed set to 7500 rpm
  • DAQ shifters can switch on Tracker (power-step 3).

-- PierreSaouter - 15-Aug-2010


This topic: Main > AmsTracker > TTCSRotate > TtcsPortDown
Topic revision: r1 - 2010-08-15 - PierreSaouter
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2019 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback