Check list for HW deployment on Q1 2008

The aquisition of 34 mid-range servers and 60 storage arrays will replace RAC1 (named RAC5, names to be ITRAC5xx, ITSTOR5xx) and create a new RAC6 (named ITRAC6xx, ITSTOR6xx, racks EK03-EK11).

Networking

  • Contacts: Marc Collignon, David Parra-Arroyo, Eric Sallaz
  • Current state (2008.01.10): Installed on RAC6. HW ready for RAC5
  • Needs:
    • need for RAC1+RAC6:
    • 2+2 switches for private network with possible uplink
    • 2+2 switches for public network (48 port each)
    • 1+1 switches for console management
    • 1+1 IP-Service
    • 60+60 IP addresses (20 publicIP + 20 virtualIP + 20 backups)

Console

  • Andras Horvath, console.support
  • Current state (2008.01.10): Installed LXC1EK13 on RAC6. Available for RAC5.
  • Needs:
    • 1+1 headnode (2 headnodes of RAC1 will stay, one new for RAC6)
    • mid-range servers will use IMPI (over LAN, no headnode needed)
    • RAC1 headnodes out of warranty, Andras prefer to replace only in case of failure, they have them in stock

HW installation

  • Tim Whibley
  • Current state (2008.01.10): rails with 4weeks delay, should arrive 5W2008;storage should arrive soon; servers expected 5W2008. Tim and Sam to coordinate installation. Removal of RAC1 after 23rd January
  • Needs:
    • 30+30 storage arrays
    • 17+17 mid-range servers (2U)
  • Rails
As only 76 out of 230 pairs will be received, Helge ordered 17 Dell rails for RAC6.
Delivery due in two weeks. 
Moreover, we requested 8 rails pairs for RAC5
so that we could set-up the two ATLAS clusters (Helge will 
inform you about the final decision). 

If all goes ok we could have all RAC6 ready  and a part of RAC5, with the 
following LHC experiments production RACs: 

 -   CMS, LHCb, WLCG and the downstream capture boxes on RAC6 (Dell rails)  
 -  ATLAS offline and online on RAC5 (8 pairs from the current batch) 

and be ready for CCRC'08  by April 14th, with a very tight schedule.  

Fiber channel

  • Contacts: Andras Horvath, Tim Whibley
  • Current state (2008.01.10): RAC6 installed. RAC5 - hw and cables already at CERN, ready to install
  • Needs:
    • 8+8 QLogic SANBox5600 (with SFPs)
    • FC cables

HW readiness

Done Date Description Due date People
done 11 January 2008 FC switches and cables 4W2008 TimWhibley
done 16 January 2008 Net switches 4W2008 MarcCollignon
done 16 January 2008 Headnode RAC6 4W2008 AndrasHorvath
    Rails for racks 5W2008 TimWhibley
done 14 February 2008 Storage arrays 4W2008 TimWhibley
    Midrange servers 4W2008 TimWhibley

RAC1 / RAC5

Done Date Description Due date People
done 11 December 2007 Ask move of FC switches to keep Compass on RAC1 50W2007 MA,JW,TimWhibley
done 17 December 2007 Move Compass to use switches in storages rack 51W2007 JW
done 14 January 2008 Move int8r to RAC4 2W2008 Luca
done 10 January 2008 Move int2r to RAC4 2W2008 Jacek
done 19 December 2007 move int3r to int11r 2W2008 Miguel
done 11 January 2008 move int4r to int12r 2W2008 Miguel
done 14 December 2007 Free int6r 2W2008 Miguel
done 7 January 2008 Free int5r 2W2008 Andrea,JW
done 23 January 2008 Free 'itrac01' 3W2008 MA,FIO
done 14 February 2008 remove RAC1 servers 4W2008 PhyDB,FIO
    connect headnode to RAC2 4W2008 FIO
    Install new servers 5W2008 FIO
done 14 February 2008 Install new storages 5W2008 FIO
done 14 February 2008 Install new switches 5W2008 CS
done 10 January 2008 Install new headnodes (not needed) 5W2008 FIO
    Configure network/IPservices 6W2008 FIO
    Configure headnodes 6W2008 FIO
    Configure storages 6W2008 FIO
    Configure disks 6W2008 FIO
    Stresstest new HW 6W2008 FIO
    Install OS+Oracle SW 7W2008 SysAdmin+PhyDB

RAC6 (racks EK03-EK11)

Done Date Description Due date People
    Install new servers   FIO
done 14 February 2008 Install new storages 6W2008 FIO
done 21 January 2008 Install new switches 6W2008 CS
done 21 January 2008 Install new headnodes 6W2008 FIO
    Configure network/IPservices 6W2008 FIO
    Configure headnodes 6W2008 FIO
    Configure storages 6W2008 FIO
    Configure disks 6W2008 FIO
    Stresstest new HW   FIO
    Shield RAC front   FIO
    Install OS+Oracle SW   SysAdmin+PhyDB

Topic attachments
I Attachment History Action Size Date Who Comment
PDFpdf Infos_Racks_ED_impaire.pdf r1 manage 198.2 K 2008-01-30 - 15:14 MiguelAnjo Racks configuration RAC5
Edit | Attach | Watch | Print version | History: r18 < r17 < r16 < r15 < r14 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r18 - 2008-02-27 - MiguelAnjo
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    PSSGroup All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2020 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback