Closed Actions, Diagnostics

Assigned to Start date Description State Result
K.Hanke, M.Pasini 2007-09-26 collect the missing information for the emittance meter specs https://edms.cern.ch/cedar/plsql/doc.info?cookie=6972219&document_id=873255&version=1 edit
U.Raich 2007-09-26 communicate rack space needed for chopper line wire scanners reported 22 October 2007 edit
E.Bravin 2007-09-26 draft a time planning for emittance meter D.Gerard reported 19 November 2007. edit
C.Vuitton, Y.Cuvet 2007-09-26 Working drawings for CCDTL inter-module regions including diagnostics and magnets first version available Jan 2008 edit
U.Raich 2007-09-26 decision on controls and read-out for chopper line wire scanners reported 18 February 2008 edit
U.Raich, C.Dutriat 2007-10-08 Make technical choice for H and V SEM grids reported 22 October 2007 edit
U.Raich 2007-10-22 Confirm/update Linac4 diagnostics budget not completed - now obsolete. edit
K.Hanke 2007-10-22 Organise the application programming reported 19 November 2007 edit
U.Raich 2007-10-22 Collect the information on alignment and communicate it to F.Gerigk Soby/Lefevre/Bravin reported 19 November 2007 edit
U.Raich 2007-11-19 Start design of a D-plate Started (see minutes 07/04/2008). edit
U.Raich 2007-12-03 Follow up VME crates for 3MeV test place with J.Serrano and C.Rossi reported 17 December 2007 edit
M.Pasini 2008-01-14 clarify alignment of beam diagnostics M. Jones explained the alignment strategy (see minutes 07/04/2008). edit
U.Raich 2008-01-14 Produce mandate for the contribution of the BI group to the Linac4 project and communicate it to M.Vretenar Replaced by action to produce a work package description. edit
U.Raich 2008-01-14 Produce EVM document for Linac4 diagnostics closed 18/12/08, not completed at this date; BI responsibility and no longer followed up by this working group edit
U.Raich 2008-01-14 Produce budget breakdown per year and communicate it to M.Vretenar closed 18/12/08, not completed at this date; BI responsibility and no longer followed up by this working group edit
G.Tranquille 2008-02-06 Clarify feasibility of 0.75 mm wire spacing for SEM-grid of emittance meter. down to 0.35mm feasible; reported 18 February 2008 edit
B.Dehning 2008-02-06 Contact urgently C.Rossi to request rack space in the Linac4 equipment hall for the BLM electronics. B.Dehning has contacted C.Rossi by e-mail on 4 February 2008 edit
R.Scrivens 2008-02-06 Contact R.Principe and C.Rossi to remind them that a compressed air distribution system will soon be required. Completed. R.Scrivens has contacted R.Principe, who has contacted BI, VAC and ATB to clarify requirements. Reported in e-mail of 20.02.2008. edit
B.Dehning 2008-02-06 Provide BLM drawings to Y.Cuvet. Done. edit
U.Raich 2008-02-06 Prepare cost comparison between CEA and CERN fabrication of movable diagnostics bench. Movable diagnostics bench will most probably not be fabricated by CEA. edit
K.Hanke 2008-02-06 Ask for an official request by the core team to clarify the responsibilities for the development of Linac4 application software. Done. It seems that OP is responsible. edit
M.Eshraqi 2008-02-06 Provide detailed beam loss distribution along the Linac4-to-PSB transfer line to allow the determination of the ideal locations for the BLMs. Done. See minutes of April 7th 2008. edit
B.Holzer 2008-02-06 Try to identify somebody available to do FLUKA simulations for Linac4. See minutes 19/05/2008. edit
E.Sargsyan 2008-02-06 Provide detailed beam loss distribution along Linac4 to allow the determination of the ideal locations for the BLMs. edit
K.Hanke 2008-03-10 Define preliminary location of BLMs in the new transfer line in high dispersion regions. Done. edit
K.Hanke 2008-04-07 Contact R. Scrivens to make sure that a solution can be found to control and read out the emittance meter needed for source characterisation at the 3 MeV test stand. See minutes 09/06/2008. edit
B.Mikulec 2008-04-07 Determine the approximate number of BLMs to be installed in the Linac4 to PSB transfer line. See minutes 09/06/2008. edit
U.Raich 2008-05-08 Contact T.Zickler to identify a (2) appropriate spectrometer magnet(s). replaced by new action on 1 September 2008 edit
U.Raich 2008-05-26 Produce a work package description of the project. Once approved by the concerned people, communicate to M.Vretenar together with the EVM document and a spending profile. closed 18/12/08, not completed at this date; BI responsibility and no longer followed up by this working group edit
K.Hanke 2008-05-29 Provide to CO user specifications and timescale for the development of the emittance scanner application. Identify an Indian collaborator who can help develop the application. See minutes 09/06/2008 and 23/06/2008. edit
R.Scrivens 2008-05-29 Contact C.Bal to finalise the compressed air installation for the LEBT Faraday Cup and SEMGrids. C.Bal has been contacted and will follow up the issue. edit
U.Raich 2008-05-29 Control if cabling (signal plus HT) has been foreseen for slits of emittance scanner. Otherwise add to the cable planning. U.Raich has sorted this out with C.Rossi. edit
E.Bravin 2008-05-29 Provide a -1 kV power supply and cabling for the FC and a +300 V power supply and cabling for the SEMGrids. Cabling plus a separate power supply is needed for the slit of the emittance scanner. Identify a suitable ADC for the FC readout. Power supplies OK; the CERN ADC will be used; C.Dutriat will follow up the cabling. edit
A.Lombardi 2008-06-17 Inform Y.Cuvet that he should update the drawings of the CCDTL and provide him with the necessary information. Done. edit
U.Raich 2008-06-25 Contact A.Lombardi for detailed optics simulations for the spectrometer design and in general for the open issues concerning the movable diagnostics bench. Done. G.Bellodi will take care of this task. edit
K.Hanke 2008-06-25 Contact C.Rossi to find out when the wire scanners have to be installed in the chopper line and inform C.Vuitton. The EDMS document has been forwarded to C.Vuitton and a link has been added at the Minutes summary page. edit
U.Raich 2008-06-25 Obtain information about the Feshenko monitor: offer, timescale for production, design details. closed 18/12/08; an offer from INP is available; BI is following up the procurement edit
U.Raich 2008-07-11 Contact P.Ausset to find out what will happen to the diagnostics line of the 3 MeV test stand once the tests will be finished. Done. G.Bellodi will take care of this task. edit
U.Raich 2008-09-01 Contact the section of Y.Kadi to communicate the specifications for the 2 dumps required for the movable bench and to find out the time scale for their design. Done. No design effort can be provided before the end of 2008. edit
K.Hanke 2008-09-01 Send a priority list for drawing jobs to P.Bourquin. Done. edit
U.Raich 2008-09-01 Contact T.Zickler to communicate the specifications for the spectrometer magnet for the movable bench and try to identify a suitable magnet. closed 18/12/08, not completed at this date; negotiations to get a spectrometer from CEA under way edit
L.Soby 2008-09-01 Check whether the PUs in the LT and LTB line have to be replaced to operate with Linac4. The PUs will all be replaced (avoid normalisation with transformer measurement), but the design of the new pickups is still pending. edit
U.Raich 2008-09-01 Add installation of cables for BI equipment in LT/LTB line to BI work package. closed 18/12/08, not completed at this date; BI responsibility to complete the work package description; not followed up by this working group edit
C.Dutriat 2008-11-20 Identify slow wire scanners that can be installed as soon as possible in chopper line. Follow up activation issue with RP and C.Rossi as 3 MeV test stand responsible. edit
U.Raich 2008-12-16 Check longitudinal dimensions of BI equipment for diagnostics movable bench with equipment specialists and give feedback to G.Bellodi. Done. See minutes of January 19th 2009. edit
R.Versaci 2009-12-16 Provide the energy deposition matrix around the H0/H- dump region. Done. Email sent with this information the 22nd of January 2010. edit
B.Holzer 2009-12-16 Provide a number for the min. detectable BLM signal. See table below. edit

-- KlausHanke - 18 Sep 2007

Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r3 - 2008-06-30 - FrankGerigk
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright