Assigned to Start date Description State Result K.Hanke, M.Pasini
2007-09-26
collect the missing information for the emittance meter specs
open closed
https://edms.cern.ch/cedar/plsql/doc.info?cookie=6972219&document_id=873255&version=1
edit
U.Raich
2007-09-26
communicate rack space needed for chopper line wire scanners
open closed
reported 22 October 2007
edit
E.Bravin
2007-09-26
draft a time planning for emittance meter
open closed
D.Gerard reported 19 November 2007.
edit
C.Vuitton, Y.Cuvet
2007-09-26
Working drawings for CCDTL inter-module regions including diagnostics and magnets
open closed
first version available Jan 2008
edit
U.Raich
2007-09-26
decision on controls and read-out for chopper line wire scanners
open closed
reported 18 February 2008
edit
U.Raich, C.Dutriat
2007-10-08
Make technical choice for H and V SEM grids
open closed
reported 22 October 2007
edit
U.Raich
2007-10-22
Confirm/update Linac4 diagnostics budget
open closed
not completed - now obsolete.
edit
K.Hanke
2007-10-22
Organise the application programming
open closed
reported 19 November 2007
edit
U.Raich
2007-10-22
Collect the information on alignment and communicate it to F.Gerigk
open closed
Soby/Lefevre/Bravin reported 19 November 2007
edit
U.Raich
2007-11-19
Start design of a D-plate
open closed
Started (see minutes 07/04/2008).
edit
U.Raich
2007-12-03
Follow up VME crates for 3MeV test place with J.Serrano and C.Rossi
open closed
reported 17 December 2007
edit
M.Pasini
2008-01-14
clarify alignment of beam diagnostics
open closed
M. Jones explained the alignment strategy (see minutes 07/04/2008).
edit
U.Raich
2008-01-14
Produce mandate for the contribution of the BI group to the Linac4 project and communicate it to M.Vretenar
open closed
Replaced by action to produce a work package description.
edit
U.Raich
2008-01-14
Produce EVM document for Linac4 diagnostics
open closed
closed 18/12/08, not completed at this date; BI responsibility and no longer followed up by this working group
edit
U.Raich
2008-01-14
Produce budget breakdown per year and communicate it to M.Vretenar
open closed
closed 18/12/08, not completed at this date; BI responsibility and no longer followed up by this working group
edit
G.Tranquille
2008-02-06
Clarify feasibility of 0.75 mm wire spacing for SEM-grid of emittance meter.
open closed
down to 0.35mm feasible; reported 18 February 2008
edit
B.Dehning
2008-02-06
Contact urgently C.Rossi to request rack space in the Linac4 equipment hall for the BLM electronics.
open closed
B.Dehning has contacted C.Rossi by e-mail on 4 February 2008
edit
R.Scrivens
2008-02-06
Contact R.Principe and C.Rossi to remind them that a compressed air distribution system will soon be required.
open closed
Completed. R.Scrivens has contacted R.Principe, who has contacted BI, VAC and ATB to clarify requirements. Reported in e-mail of 20.02.2008.
edit
B.Dehning
2008-02-06
Provide BLM drawings to Y.Cuvet.
open closed
Done.
edit
U.Raich
2008-02-06
Prepare cost comparison between CEA and CERN fabrication of movable diagnostics bench.
open closed
Movable diagnostics bench will most probably not be fabricated by CEA.
edit
K.Hanke
2008-02-06
Ask for an official request by the core team to clarify the responsibilities for the development of Linac4 application software.
open closed
Done. It seems that OP is responsible.
edit
M.Eshraqi
2008-02-06
Provide detailed beam loss distribution along the Linac4-to-PSB transfer line to allow the determination of the ideal locations for the BLMs.
open closed
Done. See minutes of April 7th 2008.
edit
B.Holzer
2008-02-06
Try to identify somebody available to do FLUKA simulations for Linac4.
open closed
See minutes 19/05/2008.
edit
E.Sargsyan
2008-02-06
Provide detailed beam loss distribution along Linac4 to allow the determination of the ideal locations for the BLMs.
open closed
edit
K.Hanke
2008-03-10
Define preliminary location of BLMs in the new transfer line in high dispersion regions.
open closed
Done.
edit
K.Hanke
2008-04-07
Contact R. Scrivens to make sure that a solution can be found to control and read out the emittance meter needed for source characterisation at the 3 MeV test stand.
open closed
See minutes 09/06/2008.
edit
B.Mikulec
2008-04-07
Determine the approximate number of BLMs to be installed in the Linac4 to PSB transfer line.
open closed
See minutes 09/06/2008.
edit
U.Raich
2008-05-08
Contact T.Zickler to identify a (2) appropriate spectrometer magnet(s).
open closed
replaced by new action on 1 September 2008
edit
U.Raich
2008-05-26
Produce a work package description of the project. Once approved by the concerned people, communicate to M.Vretenar together with the EVM document and a spending profile.
open closed
closed 18/12/08, not completed at this date; BI responsibility and no longer followed up by this working group
edit
K.Hanke
2008-05-29
Provide to CO user specifications and timescale for the development of the emittance scanner application. Identify an Indian collaborator who can help develop the application.
open closed
See minutes 09/06/2008 and 23/06/2008.
edit
R.Scrivens
2008-05-29
Contact C.Bal to finalise the compressed air installation for the LEBT Faraday Cup and SEMGrids.
open closed
C.Bal has been contacted and will follow up the issue.
edit
U.Raich
2008-05-29
Control if cabling (signal plus HT) has been foreseen for slits of emittance scanner. Otherwise add to the cable planning.
open closed
U.Raich has sorted this out with C.Rossi.
edit
E.Bravin
2008-05-29
Provide a -1 kV power supply and cabling for the FC and a +300 V power supply and cabling for the SEMGrids. Cabling plus a separate power supply is needed for the slit of the emittance scanner. Identify a suitable ADC for the FC readout.
open closed
Power supplies OK; the CERN ADC will be used; C.Dutriat will follow up the cabling.
edit
A.Lombardi
2008-06-17
Inform Y.Cuvet that he should update the drawings of the CCDTL and provide him with the necessary information.
open closed
Done.
edit
U.Raich
2008-06-25
Contact A.Lombardi for detailed optics simulations for the spectrometer design and in general for the open issues concerning the movable diagnostics bench.
open closed
Done. G.Bellodi will take care of this task.
edit
K.Hanke
2008-06-25
Contact C.Rossi to find out when the wire scanners have to be installed in the chopper line and inform C.Vuitton.
open closed
The EDMS document has been forwarded to C.Vuitton and a link has been added at the Minutes summary page.
edit
U.Raich
2008-06-25
Obtain information about the Feshenko monitor: offer, timescale for production, design details.
open closed
closed 18/12/08; an offer from INP is available; BI is following up the procurement
edit
U.Raich
2008-07-11
Contact P.Ausset to find out what will happen to the diagnostics line of the 3 MeV test stand once the tests will be finished.
open closed
Done. G.Bellodi will take care of this task.
edit
U.Raich
2008-09-01
Contact the section of Y.Kadi to communicate the specifications for the 2 dumps required for the movable bench and to find out the time scale for their design.
open closed
Done. No design effort can be provided before the end of 2008.
edit
K.Hanke
2008-09-01
Send a priority list for drawing jobs to P.Bourquin.
open closed
Done.
edit
U.Raich
2008-09-01
Contact T.Zickler to communicate the specifications for the spectrometer magnet for the movable bench and try to identify a suitable magnet.
open closed
closed 18/12/08, not completed at this date; negotiations to get a spectrometer from CEA under way
edit
L.Soby
2008-09-01
Check whether the PUs in the LT and LTB line have to be replaced to operate with Linac4.
open closed
The PUs will all be replaced (avoid normalisation with transformer measurement), but the design of the new pickups is still pending.
edit
U.Raich
2008-09-01
Add installation of cables for BI equipment in LT/LTB line to BI work package.
open closed
closed 18/12/08, not completed at this date; BI responsibility to complete the work package description; not followed up by this working group
edit
C.Dutriat
2008-11-20
Identify slow wire scanners that can be installed as soon as possible in chopper line. Follow up activation issue with RP and C.Rossi as 3 MeV test stand responsible.
open closed
edit
U.Raich
2008-12-16
Check longitudinal dimensions of BI equipment for diagnostics movable bench with equipment specialists and give feedback to G.Bellodi.
open closed
Done. See minutes of January 19th 2009.
edit
R.Versaci
2009-12-16
Provide the energy deposition matrix around the H0/H- dump region.
open closed
Done. Email sent with this information the 22nd of January 2010.
edit
B.Holzer
2009-12-16
Provide a number for the min. detectable BLM signal.
open closed
See table below.
edit