CCDTL: kick-off meeting for production of 7 CCDTL modules for Linac4 (#3888, #3889), July 13 - 16, 2009

Participants:

BINP, Novosibirsk: A. Tribendis, Y. Kryuchkov
VNIITF, Snezhinsk: M. Naumenko, D. Vavasov
CERN: M.Vretenar, M.Pasini, F.Gerigk, R.Wegner, P.Bourquin, T. Kurtyka, E. Page, S. Sgobba, C. Saint-Jal, M. Savino, G. DeMichele, G. Favre, J. Stovall, R. Maccaferri, L. Evans, A. Lombardi, L. Soby, E. Bravin, T. Zickler

list of talks:

Indico meeting 64194

supporting documents for this meeting

Technical summary (F. Gerigk)


1. ISTC contract situation
2. Construction and cooling
3. Support structure and alignment
4. RF simulations and structure dimensions
5. Vacuum and ports
6. Material orders
7. Quality assurance and future meetings
8. Intercavity sections
9. List of actions

Main results:

1. ISTC contract situation

After the welcome address by L. Evans M. Vretenar started the session with a presentation on the construction status of Linace.Then T. Kurtyka gave an overview of the preparation for contracts #3888 and #3889, which started approximately one year ago. The regular project #3888 is supported by the ISTC with 916 k$ and includes the structure design, construction of drift tubes, RF tuning, design of support frames, testing and assembly at BINP and CERN, and the transport to CERN. The partner project #3889, which is fully funded by CERN includes the design of the cavities, drawings, prepration for construction and the construction of the cavities. One of the important points for CERN was to establish a strong contractual link between the projects so that it is clear that CERN will only engage itself if both contracts go ahead. T. Kurtyka also stressed that this is probably one of the last big projects, which the ISTC can support with a significant financial contribution. This was followed by a presentation of A. Tribendis on the details of the contracts, which has been ratified recently. After the cut in funding all parties had to make an effort to save the project. The measures were:

  • CERN pays an additional 185 k$ to project #3888, but reduces the amount for project #3889 by 50 k$. The additional sum of 135 k$ paid into the project was the maximum allowed by CERN rules (10% of the originally foreseen 1 350 k$)
  • It was decided not to upgrade the baking oven at VNIITF, which would be necessary to bake the longest CCDTL structures. The baking was intended to uncover problems with the copper plating of the tanks. During a number of tests, however, no difficulties were found with the copper plating procedures. It was agreed that the first CCDTL modules shall be baked, and if there is no problem it should be safe not to bake the longer modules, which do not fit into the existing oven. This measure safes 50 k$ in project 3889.
  • The construction of support strucures was removed from project #3888, while the design of the support structure is still in the contract. CERN will now construct the support structures. BINP will construct a test frame, which will be used for the test assemblies of all modules at BINP.

The total funding can be summarised as follows:

ISTC contribution to #3888 (regular project) $ 915 884
CERN contribution to #3888 $ 185 000
CERN funding of #3889 $ 1 300 000
total budget for both projects (excluding material deliveries by CERN) $ 2 400 884

out of this total budget 600 k$ are allocated for BINP and 1 800.884 k$ are allocated to VNIITF.

Payment schedule for CERN:

  #3889 #3888
imminent payment 650 k$ 37 k$
2nd payment after completion of 3d module by VNIITF: 390 k$ after reception of 3d module at CERN: 148 k$
3d payment after completion of 5th module by VNIITF: 260 k$  

Planning: planning.png
Figure 1: Overall project planning.

The work distribution is shown in Figure 2.

CCDTL_integration.png Figure 2: work distribution between the institutes.

2. Construction and cooling

Drift tube construction:

  • It was agreed to braze the end tips onto the drift tube body, rather than to use EBW as originally foreseen.
  • The drift tubes are brazed with oversized pieces and then machined to the desired dimensions.
  • A brazing foil will be used to ensure good leak tightness. Any silver alloys coming to the surface will be machined off, when the drift tubes are machined to the final dimensions.
  • It was agreed that the drift tubes will have 3 target holders each (on the circumference) to be used with a laser tracker.
  • The construction of the drift tube is illustrated in Figure 3.

drift-tube_brazing.png
Figure 3: drift tube construction

Stem-drift tube joint and stem-tank joint:

  • there are 2 options for joining the stem to the drift tube:
    • EBW (3 mm penetration). This option has the risk that the EBW will introduce a certain non-perpendicularity.
    • Brazing: this seems attractive because it is easier to fix both pieces into position when they are put into the brazing oven. The copper of the stem will annealed in any case because of the top part of the stem (made out of steel) will be brazed to the stem.
  • A Helicoflex joint (HNRV) will make the vacuum/RF contact between the drift tube and the stem as indicated in Figure 4.

stem-tank.png
Figure 4: connection of stem to tank body.

Prototyping:

  • BINP will construct 2 prototype drift tubes including a dummy volume and the alignment girder to verify the construction approach. CERN will deliver the necessary materials.

Water connections

  • It was agreed to connect several water circuits in series. The limitation is a maximum temperature difference of 50 deg, a maximum flow speed of 1.5 m/s, and a maximum pressure drop of 5 bars.
  • It was agreed to use SERTO fittings with self-sealing conical screws where ever possible (see Figure 5). In case the material is not thick enough to allow cutting the threads, the material thickness should be increased so that a thread can be made. If access conditions forbid this technique, SERTO fittings will be welded into position.
  • Pressure tests of all cooling circuits will be made at 16 bars.
  • If available the SERTO fittings will be bought in Russia. If not the fittings can be ordered via CERN. The SERTO fittings will be paid for by VNIITF/BINP.
  • Looking downstream, the water manifolds will be mounted on the right hand side.

SERTO.png
Figure 5: SERTO fittings with concial self sealing threads.

3. Support structure and alignment

The alignment of drift tubes inside the tank was presented by A. Tribendis. The concept uses a mechanical alignment, which was considered as suitable but work intensive. Instead it was suggested to make use of the laser tracker, which is available at BINP and to include 3 target holders on each drift tube. Whether these target holders will be used by BINP or not, it was agreed to include them in the drift tube design, so that a laser tracker can be used if needed.

Summary of the discussion on the support structure:

  • VNIITF and BINP are developing the design for the support. They will provide intermediate drawings (in Russian) for integration checks. The construction drawings will be provided in English and will have to be adapted by CERN for production in Western industry. The design of the support also includes the support of the quadrupoles between the cavities. However, CERN will provide details of the alignment tables, which are foreseen to adjust the position of the quadrupoles.
  • BINP/VNIITF will write an alignment procedure, which explains the concept.
  • It was agreed to relax the tolerances for the alignment of the drift tubes with respect to the ideal beam axis from -+ 0.1 mm to -+ 0.3 mm. The precision for the alignment of the quadrupoles stays at -+ 0.1 mm.
  • For the test assembly at BINP, a test frame is under construction, which is bolted to the floor for rigidity and then levelled to provide an ideal assembly frame.
  • The middle tank is bolted to the support, while the end tanks are free to move longitudinally and vertically on rails. It is assumed that once the module is screwed together that it will actually sit on 3 points. The other points will be shimmed or supported with adjustable screws to avoid any tension in the system and to avoid vertical movement when the structure settles. Longitudinal movement due to temperature changes is possible.
  • It needs to be understood how the alignment procedure affects the tuning of the coupling cell.

4. Simulation work
  • The shape of the drift tubes was changed by BINP. RF simulations where made with MWS to correct the gap frequencies.
  • It was found that the RF simulations of BINP and CERN agree in terms of power consumption.
  • CERN changed the dimensions of the last module (using -28 degrees as synchronous phase instead -20 degrees). The changed dimensions were given to BINP and accepted link to parameter list.
  • There is a bit of doubt on the simulation results of the coupling cells. CERN will measure the dimensions of the ISTC prototype coupling cell and give the values to BINP, where measurements of the untuned cell are available.
  • G. DeMichele showed a new coupling cell geometry, which increases the cell to cell coupling by 12% (checked at 50 MeV and for the last module). In the last module the coupling is increased from 0.52% to 0.59%. This geometry shall be used for the last few modules.

5. Vacuum and ports
A. Tribendis showed the concept for the vacuum system as it was discussed via emails during the last months. The basic concept is shown in Fig. 6

vacuum.png
Figure 6: Layout of vacuum pumps and gauges on the CCDTL.

  • It was agreed that all tuning ports are located on the right upper quadrant of the cavities (45 degrees from 12'o clock, looking downstream) if necessary. If they fit within the outline of the coupling cells they can also be located at 90 degrees on the right hand side. RF pick-up ports are located on the left hand side of the modules with the exception of one pick-up port, which is on the coupling cell that is on the right-hand side of the module.
  • It was agreed to use the same ports for RF pick-ups and vacuum gauges (DN 40 CF, interior port diameter: 29 mm). There is one such port on each cell. During high-power testing all 5 ports will be used for RF monitoring and there will be a vacuum gauge on the waveguide port (together with a pump). In operation only 2 ports are used for LLRF and in total 5 ports out of 14 free coupling cell ports will be used for vacuum gauges.
  • RF coupler port: using the standard port size of Linac4 (inside: 303x50 mm) gives a longer cut-off wave-guide (between cavity and T waveguide) than for the CCDTL prototypes, which leaves more space for mounting the coupler with screws.
  • Half cavity flanges plus flanges of coupling cells will be copper plated.
  • Rectangular wave-guide flanges and the surfaces around the stem/tank Helicoflex gaskets will not be copper plated.
  • There are 2 ion pumps per module, and 2 roughing pumps on 2 waveguide couplers for the whole CCDTL section.
  • Someone from the CERN vacuum group will be present during assembly and first vacuum test (with Helicoflex gaskets) of 1st module at BINP.
  • It was found that there was a misunderstanding concerning the inner diameter of the ports for the ion pumps. CERN had assumed 150 mm to get sufficient pumping speed, while BINP/VNIITF had assumed 100 mm as for the ISTC prototype. 150 mm in diameter is too big to fit between the cooling channels. In order to have sufficient pumping speed one of the following 3 options has to be applied:
    • use a 100 mm diameter with an increased conductance (EP will check if Varian ion pumps are available for that port size, AT will try to increase the conductance),
    • use a “racetrack” shaped port on the cavity, which then transforms into a DN 150 CF flange (inner diameter 150 mm, outer: 202 mm),
    • use a 150 mm port and connect cooling channels “above” and “below” the port instead of having them surround the cavity (this way they are in fact closer to the hot spots than in the old approach).

List of ports on the CCDTL modules:

ports ports p. module total number flange type drawing inner outer comment
vacuum gauge/RF pick-up 5 35 DN40 CF STDVFUHV0093 29.7 70  
tuners coupling cells 4 28 DN63 CF STDVFUHV0092 60 114  
tuners accelerating cells 6 42 DN100 CF STDVFUHV0094 84.9 152  
vacuum pumps 2 14 DN150 CF STDVFUHV0049 150 202  
RF coupler 1 7 Helicoflex   303 x 50 xx custom made
beam pipe 6 42 Helicoflex   xx xx  

6. Material orders

The following points were discussed:

  • CERN will provide certificates for the steel and copper pieces, which are delivered to Russia.
  • CERN will prepare the delivery of all pieces (to BINP) needed to make 2 drift tube prototypes (including Helicoflex joints for stem/tank: HNRV 100 diamT=3.4, alum, 47.1x53.9 c opening at inside), BINP will enquire how to ease the customs procedure,
  • FG will send drawings of all needed conflat flanges together with preliminary amounts to CSJ, so that these pieces can be reserved for the CCDTL,
  • The first CCDTL module will be tested with Helicoflex gaskets at BINP, these gaskets must be ordered 4 months in advance, CERN will order all CCDTL gaskets (+ wave-guide gaskets of all structures) as soon as the number and size of all gaskets is known,
  • Steel tubes for ports will most likely come out of CERN stocks (either 304 or 316), bulk steel pieces for RF ports most likely from solid cylinders available at CERN,
  • delivery of all material should be foreseen for the middle of October. We assume that ISTC can remove all customs procedures, so that the transport (CERN-VNIITF-BINP) should not take more than one week.
  • Bolts for test assembly are provided by BINP, CERN will buy bolts for final assembly at CERN,
  • VNIITF prefers to use M8 screws for the coupler port, CERN will check if M8 screws can be used for all RF ports instead of M6,

The following list of materials was agreed:

stainless steel length outer diameter wall thickness number delivery status comment
[mm] [mm] [mm]
rods 280 30 solid 50 ready for delivery  
tubes 200 15 1.5 50 ready for delivery  
drift tube body 250 120 solid 55 ready for delivery  

stainless steel length outer diameter wall thickness number delivery status comment
[mm] [mm] [mm]
half cavities 405-575 610 buckets 46 ready for delivery agreed with manufacturer and VNIITF that the sizes for positions 19 and 20 can be reduced to 550/415 and 560/425
cooling tubes 600 8 1 50 ready for delivery cooling tubes inside of stems
coupling cells 170 300 50 16 ready for delivery  
coupling cell noses 125 305 solid 32 ready for delivery  
tubes for DN100 CF 150 88.9 2 48 delivery  
tubes for DN63 CF 150 63 1.5 32 ready for delivery  
tubes for DN40 CF 150 33.7 2 40 ready for delivery  
bulk cylinders for DN150 CF 80 ?? solid 16 t.b.c. pumping ports

stainless steel length width height number delivery status
[mm] [mm] [mm]
blocks for RF ports ~400 ~80 ~100 9 probably from bulk cylinders available at CERN

conflat flanges blanks purpose drawings drawings of blanks tube inner/outer diameter delivery status
DN40 CF 80 RF pick-ups/vacuum gauges STDVFUHV0093 STDVFUHV0005 29.7/33.7 ready for delivery
DN63 CF 64 tuners coupling cells STDVFUHV0092 STDVFUHV0007 60/63 ready for delivery
DN100 CF 96 tuners accelerating cells STDVFUHV0094 STDVFUHV0009 84.9/88.9 ready for delivery
DN150 CF 32 vacuum pumps (size t.b.c.) STDVFUHV0049     -

7. Quality assurance and meeting schedule

  • After the production of the modules CERN will receive "as built" 3D models in Solid Works and execution drawings in Autocad (in English) using the GOST standard for tolerances.
  • For the frames CERN will receive a 3D model in Solid Works and CERN will then produce execution drawings.
  • Each cavity will be accompanied by paper containing all quality assurance tests (metrology, leak tests, surface quality, flow rate, pressure test, temperature history of heat treatments, RF measurements)
  • Another document will be provided to CERN that describes the test procedure (where/how pumps are connected, how leak tests are done, procedure for metrology),
  • We should foresee the participation of BINP at high-power tests of 1st module (or more),

Meeting schedule:

subject location time
ISTC/VNIITF/CERN management + technical meeting CERN October 2009
results of drift tube mock-up BINP January 2010
technical meeting CERN March 2010
first module ready and partly copper plated VNIITF June 2010
technical meeting CERN October 2010

8. Intercavity sections

R. Maccaferri presented a sketch on the intercavity sections. The following points were discussed:

  • There were some uncertainties about the available space between the cavities. This will be verified.
  • CERN needs to decide whether to extend the supports so that inter-module elements can be placed there.
  • Flanges between cavities and modules use Helicoflex joints.
  • The pipes between the cavities and modules are CERNs responsibility.
  • Alignment arms on the support frame are CERNs responsibilities.
  • Figure 7 shows the available space for magnets between the cavities.

intercavity_space_for_magnets.png
Figure 7: intercavity space for magnets

9. Action list:

action institute/person status/result completed
complete first payment to ISTC CERN, T. Kurtyka, M. Vretenar done 13 August 2009
provide size and shape of target holders on the drift tubes for laser tracking system CERN, Y. Cuvet done: extract from drawing of DTL drift tubes  
include target holders for laser tracker target on the drift tubes BINP, A. Tribendis done  
provide power loss estimation for the Helicoflex connection of stem and tank, where the joint sits on non-copper plated steel surfaces BINP, A. Tribendis done: 1 - 1.7% in Q0 (if Cu instead of steel) 12 August 2009
construction and testing (in dummy vacuum volume: vacuum tightness of all joints, pressure test, flow test, alignment principle) of 2 prototype drift tubes (one with EBW between stem and drift tube, and one with brazing) BINP, A. Tribendis done see meeting March 2010 2010-03-10
material delivery to BINP for drift tube prototypes CERN, F. Gerigk items shipped w/o Helicoflex gasket list of items shipping request in EDH 2 September 2009
cooling simulations for the case when several cooling channels are connected in series BINP/VNIITF dropped  
find out which kind of water hoses (connection of cooling circuits) are generally used/accepted at CERN CERN, R. Maccaferri done: reference from CERN stores link to CERN stores  
suggestion for high-pressure, radiation hard, semi-flexible hoses for cooling water connections BINP, A. Tribendis done: picture 1, picture 2 2009-10-09
provide drawings of an alignment table suitable for the quadrupoles between the cavities CERN, F. Gerigk, P. Bourquin, M. Jones pending  
provide written procedure for the alignment of the modules on their support BINP/VNIITF open  
provide a 3D volume that can be used for the CCDTL volumes CERN, J-P. Corso done 2D cross-section in CCDTL section 2009-10-22
provide intermediate drawings of CCDTL moduls for integration check BINP/VNIITF done drawings in EDMS (restricted access) 3 September 2009
check with intermediate drawings of CCDTL modules integration into the Linac4 tunnel (with pumps, tuners, pick-ups, cables CERN, J-P. Corso pending  
metrology check of the ISCT CCDTL coupling cell dimensions (results are indicated on the drawings for the CERN prototype) CERN, F. Gerigk done: report, drawing 1, drawing 2 2009-08-20
use new coupling hole geometry for the last few modules to increase cell to cell coupling BINP pending  
confirm the size of the pumping port after selecting one of the possible options (see vacuum) BINP/VNIITF/CERN done Vacuum port geometry 2009-11-16
check if the vacuum conductance through the pumping ports can be increased BINP, A. Tribendis done presentation 2009-08-20
check if there is VARIAN ion pump with an inner port diameter of 100 mm CERN, E. Page solved: VacIon Plus_150 17 July 2009
provide information on roughing pumps to VNIITF (size, size including T piece needed during high-power testing for the gauges) CERN, E. Page done: dimensions of vacuum equipment 22 July 2009
provide a short written description of vacuum testing procedure at BINP BINP, A. Tribendis done: procedure 2009-10-16
define size of stainless steel blocks for RF ports BINP/VNIITF done Vacuum port geometry  
reserve conflat flanges for vacuum ports CERN, F. Gerigk, C. Saint-Jal done most pieces are delivered 2009-10-21
define size of port tubes and order them F. Gerigk, A. Tribendis done  
provide testing standards, which are used in material certificates CERN, S. Sgobba done 17 July 2009
provide standards for qualification of electron beam welding CERN, S. Sgobba done 17 July 2009
discuss how/if the qualification of welders is mandatory for this contract CERN, S. Sgobba, G. Favre done Meeting October 2009  
provide dimensions and type of all needed Helicoflex gaskets 4 months before assembly of the drift tube mock-up BINP/VNIITF pending  
VNIITF will send a welding test sample to CERN according to the EU welding standards VNIITF, M. Naumenko done 2010-03-10
qualify the VNIITF welding sample CERN, S. Sgobba pending  
provide list of bolts for assembly (to be bought by CERN) BINP/VNIITF pending  
check if M8 screws can be used for all RF ports instead of M6 CERN, P. Bourquin, F. Gerigk done agreed to use M8, which enables us to use HN 200 gaskets instead of HNV 200: preliminary drawing DTL waveguide port  
We need to decide on ownership of tooling and type of tooling which might be interesting for CERN CERN, F. Gerigk, P. Bourquin, T. Kurtyka done CERN will receive the tools it wants  
decide whether to put inter-module elements on the same support as the modules CERN, F. Gerigk, R. Maccaferri done yes, elements will be put on same support SupportAlignment0809 2009-08-24
define additional support length to house the intermodule elements CERN, R. Maccaferri pending  
define the type of tables, which will be used to support the quadrupoles between the cavities of one module CERN, F. Gerigk, P. Bourquin, M. Jones pending  
calculate the increase in cell-to-cell coupling for the last module, when the new coupling slot shape is used CERN, G. DeMichele done: 13% increase from 0.52 to 0.59% 2009-07-22
provide peak electric field in center gap of each tank CERN, G. DeMichele done: table 2009-08-13
provide information on CERN EBW machine CERN, F. Gerigk, T. Tardy done: CERN EBW machine 2009-08-28
provide drawings of rectangular PIMS waveguide flange & Helicoflex joint CERN, F. Gerigk done: SPLACPMB0025, SPLACPMB0024, SPLACPMB0017, joint 2009-08-28

10. Appendix

List of items for drift tube mock-up

item material length outer diameter wall thickness quantity
drift tube bodies copper 250 120 solid 2
tubes copper 200 15 1.5 3
rods copper 280 30 solid 3
tubes stainless steel 600 8 1 3
rods stainless steel 200 60 solid 2

spring washers outer diameter: 70 mm inner diameter: 40.5 mm thickness: 4 mm uncompressed height: 5.6 mm 8 pieces
Helicoflex joints t.b.d
SERTO weld-on union type: SO51429-15 2 pieces
SERTO nut connection type: SO50021-15 2 pieces

List of Helicoflex joints

joint type size torus diameter groove dimensions groove thickness numberSorted ascending comment
half tanks HN 200 522x534 6 520x535 5   same size as for DTL sections

-- FrankGerigk - 16 Jul 2009

Topic attachments
I Attachment History Action Size Date Who Comment
PNGpng CCDTL_integration.png r1 manage 49.5 K 2009-07-22 - 16:08 FrankGerigk  
PDFpdf DTL_-_RF_port_21-09-09.pdf r1 manage 411.1 K 2009-09-21 - 16:18 FrankGerigk  
PDFpdf HELICOFLEX_PIMS.pdf r1 manage 53.5 K 2009-09-16 - 15:38 FrankGerigk  
JPEGjpg Hose_1.jpg r1 manage 71.5 K 2009-10-21 - 14:43 FrankGerigk  
JPEGjpg Hose_2.jpg r1 manage 29.0 K 2009-10-21 - 14:43 FrankGerigk  
PNGpng SERTO.png r1 manage 23.4 K 2009-07-17 - 15:10 FrankGerigk  
PNGpng Voila_Capture17.png r1 manage 163.0 K 2009-10-21 - 14:48 FrankGerigk  
PNGpng drift-tube_brazing.png r1 manage 86.3 K 2009-07-17 - 14:35 FrankGerigk  
PNGpng intercavity_space_for_magnets.png r1 manage 129.1 K 2009-07-20 - 18:22 FrankGerigk  
PNGpng planning.png r1 manage 61.0 K 2009-07-17 - 12:06 FrankGerigk  
PNGpng stem-tank.png r1 manage 19.2 K 2009-07-17 - 14:44 FrankGerigk  
PNGpng vacuum.png r1 manage 40.0 K 2009-07-20 - 14:44 FrankGerigk  

This topic: SPL > WebHome > Linac4Web > CollaborationMeetings > ISTCcollaborationMeetings > July09CCDTL
Topic revision: r31 - 2010-06-01 - FrankGerigk
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright