F. Gerigk, S. Ramberger, R. Wegner, G. DeMichele , P. Tirado
General
- Finance committee agreement to negotiate with Polland and Germany without tender. The technical collaboration papers are in progress.
- Set priorities with the design office: DTL; support for the first CCDTL module (the module is expected in January); movable tuners (possible agreement with INFN)
DTL
- Drift Tubes: pieces from 3 companies have been measured at CERN and not all are inside the specs.
PIMS
- High power test-stand in progress: tests will start in 4weeks
- Waveguide-T ready in two weeks: already machined, to be copper plated
- Water cooling system tested at 16 bars
- HFSS study of a short circuit integrated with the waveguide: a movable tuner will be used to change the coupling strength.
--
GiovanniDeMichele - 01-Oct-2010