F. Gerigk, R. Wegner , G. DeMichele

DTL

  • Prototype high power test
    • Prototype with magnets in the first DT and in the LE end-cone conditioned at 3% d.c. (width=1.5msec; repetition rate=20Hz)
    • Removed magnet in the LE end-cone for the installation of the anodizing matrix: at the moment the prototype is under vacuum

CCDTL

  • the designed support, integrated in KATIA files, shows interferences of the structure in the survey area: modifications to be applied
  • visit to Russia planned on 15-17th June

PIMS

  • Welding on the prototype finished
  • Prototype high power test
    • the test will be done in the 3MeV test stand area: concrete wall for x-rays shielding (discussion with RP group: T. Otto, M. Widorski)
    • alignment and shrinking measurements after welding ongoing

Debuncher cavity

  • +/- 80 degrees phase shift in 40usec period is possible by changing the loaded Q (QL=6000, Pcav=25kW)

-- GiovanniDeMichele - 07-Jun-2010

Edit | Attach | Watch | Print version | History: r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r1 - 2010-06-07 - GiovanniDeMichele
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright