Minutes RF structure meeting 05.02.2009

F.Gerigk, S. Ramberger, M. Schuh, G. DeMichele, F. Grespan

CCDTL

  • Kickoff Meeting 07-09.04.09
  • Awaiting authorisation from CERN Management for increased cost

PIMS

  • Status of negotiation with manufacturer (FrankGerigk)
    • production problems (cracks in surface) increase production cost
    • find new subcontractor for small cylinders to make them twice as long and cut later at CERN in order to reduce the cost

DTL

  • Status of the circuit model (FrancescoGrespan)
    • good agreement found for a simple model with 2 drift tubes and one post coupler
    • reduce model to 1 drift tube with 2 half post couplers
  • Hot Protoype (SuitbertRamberger)
    • vacuum tests not yet completed
    • test stand in SM18 not available following delays on vacuum tests
    • first high power tests at 3MeV test stand early March
    • install radiation shilding if neccessary. Contact Carlo Rossi
  • Power coupler simulations (GiovanniDeMichele)
    • HFSS, MWS simuations
    • determine scaling factor with simplified geometry

LINAC4

  • allocation of construction and storage space for all structures has to be done far in advance. Contact JeanMichelGiguet

New Meeting Time: Fridays 14.00-15.30

-- MarcelSchuh - 05 Feb 2009

Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r2 - 2009-02-05 - SuitbertRamberger
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright