Minutes Diagnostics Working Group meeting 11.10.2007

N. Alharbi, F. Gerigk, M. Pasini, S. Ramberger, C. Rossi, M. Vretenar, R. Wegner

news & facts:

  • L4 siting effort: 33 MCHF for new site, 4.2 years building time for CE -> this means DTL should be commissioned in the South Hall, now try to have klystron tunnel on surface and acc tunnel higher up,
  • pims: Yves Cuvet is reserved from Sept/Oct onwards,
  • Rosario Principe (mechanical engineer) to work with us: relations with the workshop,
  • MV ~1MCHF to increase all apertures in the TL so that they can digest the energy spread from the ramping,
  • MV: total structure cost ~12 MCHF, 3.5 pims, 5 ccdtl (8 modules), 3.5 dtl,
  • price estimate for e-beam welding of pims:

prototype
Total des activités liées à l'assemblage du prototype 115 000 CHF
Coût pour l'assemblage par FE d'une cavité prototype 11 300 CHF
Coût total de fabrication pour un prototype 126 300 CHF
12 cavités
Total des activités liées à l'assemblage des 12 cavités 18 600 CHF
Coût pour l'assemblage par FE de 12 cavités 135 800 CHF
Coût total de fabrication pour 12 cavités 154 400 CHF
Budget total pour l'assemblage de 1 prototye et 12 cav. 280 700 CHF

decisions taken:

  • FG asked about the price of 15 kCHF assumed for each movable PIMS tuner (ACCEL had quoted 28 kCHF for each tuner), MV confirmed this price by quoting price of the buncher cavity tuners: 4 kCHF for 2 smaller tuner, so 15 k for the pims tuners seems realistic
  • program for WP2 meeting agreed,
  • e-welding pims: the institute that does the prototype should also weld the whole structure due to the high price of the tooling,
  • start soon with P. Bourquin and Yves to discuss mech. approach for pims,
  • number of klystrons: RFQ:1 old, DTL: 2 new, 1 old, CCDTL 7 old, pims: 4 old, 4new, -> 19 klystrons in total,
  • decided to use PIMS for Linac4Web and not the SCL, to be presented at the upcoming HIPPI WP2 meeting,

new actions

Assigned to Start date Description State Result
FrankGerigk, MatteoPasini 2007-05-08 fix transition energies CCDTL/PIMS 50, 102 MeV edit
FrankGerigk 2007-05-08 ask for use of SF6 in circulators at GSI for new 3 MW klystrons a first test will be made without SF6 edit
Main.all 2007-05-08 redo ZTT plot for revised layout Linac4ZTT edit
FrankGerigk, RolfWegner 2007-05-08 prepare summary of pros/cons for PIMS/SCL for structure meeting SCL/PIMS comparison edit
MatteoPasini 2007-05-08 re-optimise CCDTL shunt impedance presentation edit

Updated ActionListRF

minutes by F. Gerigk

-- FrankGerigk - 12 Jun 2007

Edit | Attach | Watch | Print version | History: r10 < r9 < r8 < r7 < r6 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r10 - 2008-06-30 - FrankGerigk
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright