F. Gerigk, S. Ramberger, R. Wegner, G. DeMichele , P. Tirado, M. Schuh, and R. De Prisco
SPL
- Only small cryomodule (for 4 cavities) will be build until mid of 2013
DTL
- One new drift tube installed in prototype
- Black spots found on structure surface
- Detailed analysis after next HP test
- Q drop during HP tests - Analysis of Q history will be done
- One possible source: multipactoring
- Round edges for rf slot and tuners
Cavity conditioning software
- Program runs more than 6h without intervention
PIMS
- Effect of weld shrink expected between 200 - 300kHz using different method and codes
- PIMS simulation comparison between HFSS12, Superfish, MWS, gdfild
HOM
- Started simulation with electron beams
- Bug found in transverse beam dynamic module
--
MarcelSchuh - 09-Apr-2010