Y. Cuvet, F. Gerigk, J-M. Giguet, S. Ramberger, K. Schirm, R. Wegner

RFQ tuning (F. Gerigk)

  • during a meeting yesterday we agreed on a schedule with Carlo, Jose, Han, Maurizio

movable tuners (F. Gerigk)

  • IKEA test started last Friday, 2 weeks of testing should correspond to ~10 years of operation,
  • planning to run for at least one month,
  • received delivery schedule and production procedure,

CCDTL (F. Gerigk)

  • last payment to ISTC de-blocked and under processing

Helicoflex order (F. Gerigk)

  • JM and Karl will define what additional joints are needed and prepare an order,

India - some jobs for K. Schirm: (F. Gerigk)

  • define vacuum test procedure with Helicoflex together with Jan Hansen,
  • ask for vacuum test with rubber joints before visit,
  • see if we can get the material, which is needed for the production in India, within a short delay,
  • send drawings for covers of flanges and for spacers and ask Purushottam to produce these,
  • set visit date,
  • ask for welding tests, and ask which filler they want to use,

PIMS (R. Wegner)

  • Promising welding pre-test applying a cosmetic pass directly after the welding operation https://twiki.cern.ch/twiki/pub/SPL/Minutes10May2012/Pre-Test.doc.
  • Confirmation that reference surfaces for metrology targets can be circular in shape instead of rectangular (M. Jones, A. Dallocchio, L. Gentini, B. Riffaud). Waiting for decision from NCBJ to select better solution.
  • Quality Assurance Report format for all 5 PIMS elements finished, EDMS 1210268.
  • Warning NCBJ to save a long waveguide ring for module N.
  • Transport of remaining material to NCBJ is being prepared.
  • Meeting on brazing of waveguide rings:
    • For the brazing test, the material needs to be machined to a shape of the ring for a representative test (movement of the copper close to stainless steel flange depends on the copper thickness, thinner material moves more).
    • Quality Assurance documentation has been defined
    • Discussion if in worst case the 12 waveguide rings could be brazed at CERN. Work: ~ 2 weeks per ring, surface treatment should be done at CERN, other machining and thermal treatments could be done at NCBJ.
  • A preliminary metrology report for end disc M_1 has been received https://twiki.cern.ch/twiki/pub/SPL/Minutes10May2012/Preliminary_Report_-_End_Disc_M_1_SPLACPMM0002.pdf. Most (relaxed) specifications have been met, all relaxations have been exploit, some slight deviations that should be acceptable. New difficulties seen are the directions of cooling channels: for example channel 1 has an angle of -0.6, channel 2 has an angle of 0.0 towards horizontal plane. At the meeting point at a depth of 227 mm, this tilt produces a displacement of 2.4 mm of the 2 channels (channel diameter 12 mm).
  • Decisions taken: sensibilise Polish colleagues of problems but green light for full machining of end disc M_14 and another disc for module M in order to gain time.
  • Welding of 4 samples for qualification are finished in Julich, 2 rings for NCBJ are scheduled to be welded still this week - before welder goes on holidays.

-- RolfWegner - 10-May-2012

Topic attachments
I Attachment History Action Size Date Who Comment
Microsoft Word filedoc Pre-Test.doc r1 manage 231.5 K 2012-05-10 - 11:12 RolfWegner  
PDFpdf Preliminary_Report_-_End_Disc_M_1_SPLACPMM0002.pdf r2 r1 manage 3218.0 K 2012-05-10 - 12:50 RolfWegner  
Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r2 - 2012-05-10 - RolfWegner
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright