F. Gerigk, S. Ramberger, G. DeMichele , R. De Prisco

Buncher cavity

  • the cavity arrived in Geneva (not yet in CERN) from Polland (shipment on 2nd February).

DTL

  • visit to Bilbao to close the agreement
    • the drift tubes will be supplied from July 2010.
    • the drift tube for the HP test could come to CERN in few weeks
  • position of waveguides (WGs) and pick-ups on tank1,2,3 under investigation
  • DTL prototype
    • Qloaded about 15000 against 18000 at the time of the HP test.
      • transition N-type to WG to be checked
      • tightness of the bolts on the end-walls to be checked
    • Upgrade of LabVIEW data acquisition from PLC

CCDTL

  • Circuit Model:
    • simulated modes curves fit with measurements
    • difference between simulated and measured coupling cell frequency: 160kHz

PIMS

  • Schedule for construction was relaxed by 6 month
  • Decision has to be taken if structures will be welded or brazed.
    • Interesting option could be the brazing because the vacuum brazing oven will be ready at the end of the year and can fit with the schedule
  • PIMS low power measurements to be started on the 1st week of March

-- GiovanniDeMichele - 12-Feb-2010

Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r1 - 2010-02-12 - unknown
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright