F. Gerigk, S. Ramberger, K. Schirm, R. Wegner, P. Ugena-Tirado

PIMS (S. Ramberger) 4 companies have been in Spain for girder and drift tube production. DMP now announces 6 weeks of delay for the first batch of drift tube parts with respect to the agreed schedule of January. For the other parts the schedule has still not been established. A new planning is promised for 20 April. The drawings for the assembly of drift tube parts in-house has been reviewed. Several smaller issues have been detected that need to be sorted out in the next weeks. The tooling for the 4th drift tube welding and the document on the assembly procedure needs to be updated. The heat treatment of the first DTL segment has been completed successfully at CERN and the tank has been sent back to CADINOX.

PIMS (R. Wegner) New pieces for welding test sent to Juelich, arrived yesterday Summary of Visit of IPJ and CPL in Poland uploaded onto EDMS: https://edms.cern.ch/document/1141661/1 Meeting with workshop and design office will be organised to discuss acceptance tests of first test pieces which will arrive end of May to CERN

PIMS (R. Wegner) HFSS and GDfidl have been compared in order to obtain the frequency shift due to different tuning island heights. HFSS will be used for the rest of the modules. The work on the PIMS First module high power measurements publication continues.

-- RolfWegner - 15-Apr-2011

Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r1 - 2011-04-15 - RolfWegner
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright