Y. Cuvet, F. Gerigk, J-M. Giguet, G. T. Papadaki, S. Ramberger, R. Wegner, P. Ugena-Tirado
BINP shipping (F. Gerigk)
- BINP and CERN transport departments are in contact.
Jacks (F. Gerigk)
- order of remaining pieces is in preparation (Benoit & Nordine)
- modified technical specs are approved and released
Windows (F. Gerigk)
- exchanged 316 LN with 304 L on vacuum side
EVM (F. Gerigk)
PIMS (F. Gerigk , R. Wegner)
- 2nd side of disc G_2-3 with an overlength of 0.5 mm finished. Most tolerances have been met. Disc will be machined to final dimensions now.
- Problem found on supports, materials will be revised
- NCBJ search for subcontractors having a lathe suited for the PIMS production is continuing, 3 Polish companies have been contacted.
- NCBJ is working on the option to purchase a vertical lathe, particularly for the PIMS production
- The X-ray tests of the 2 Rings G_1-2 and G_13-14 could not confirm that the welds are conform to specifications. A detailed investigation will be done at CERN.
- director Pawel Krawczyk confirmed that efforts are made to buy a turning machine, and also that the PIMS now has the highest priority at the Soltan Institute.
- Tadeusz has recently visited the Soltan Institute and inquired about the production status.
PIMS (P. Ugena-Tirado)
- The second note on the PIMS tuning procedure will be finished by the end of next week, in order to prepare the IPAC publication.
--
RolfWegner - 15-Mar-2012