F. Gerigk, S. Ramberger, R. Wegner, G. DeMichele , P. Tirado, M. Schuh

General

  • Meeting on installing of L4 RF structures:
    • DTL commissioning in tunnel, other structures before installing in tunnel
    • RF windows installing in tunnel
    • Wave-guides to be installed before the cavities
  • Window tendering: review of specs next week
  • First magnets needed until March 2012 before installing CCDTL and PIMS

DTL

  • Visit to Bilbao next week

PIMS

  • Progress in preparing test area
  • Prototype measurements
  • Further simulation on tuner in wave-guide

HOM

  • CST and MWS simulation to complete HOM analysis of baseline cavities

-- MarcelSchuh - 15-Oct-2010

Topic attachments
I Attachment History Action Size Date WhoSorted ascending Comment
PowerPointppt PIMS_module_1_final_tuning.ppt r1 manage 215.5 K 2010-10-15 - 17:33 RolfWegner Results of final tuning - before cutting the tuners.
Unknown file formatpptx Status15oct.pptx r1 manage 565.8 K 2010-10-15 - 17:31 UnknownUser  

This topic: SPL > WebHome > Linac4Web > RFStructureMeetings > Minutes15October2010
Topic revision: r3 - 2010-10-15 - RolfWegner
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright