Soltan Institute will deliver the cavity around the middle of November (first estimate was June)
Q measured=19200 without helicoflex (18800 corresponds to 80% of Superfish)
DTL
High Power test
klystron switched ON and tested
21 different circuits for the water cooling (4 for the cavity body, 2 for the end-walls, 1 for the iris, 12 for the DTs, 2 for the PCs )
PLC installed to read temperatures (15/16 thermocouples: 4 for the DTs, 4 for the PCs, 3 for the tuners, 2 for the end-cones, 2 for the iris), water flow (controllers:1 general+ 7 on the cavity: 4 for the DTs, 1 for the PCs, 1 for the iris, 1 for the end-wall)
starting test next week
Meeting in ESS: they are evaluating different designs for a 352.2MHz DTL-among them also the CERN LINAC4 NC design
CCDTL
vacuum test on the CCDTL prototype is in progress to come to a decision on the pumping ports size
simulations with HFSS and MWS to check the coupling cell frequency (so far 1MHz difference with the two codes). Measurement done with a rod in the accelerating cell as well as the simulations
a technical meeting will take place at CERN on October 26th-27th-28th
a kick off meeting for the managements of all involved institutes will take place at CERN on October 29th
is likely to be produced within a cooperation between Soltan Institute, Jülich (Germany) and CERN. At CERN will be done the EB welding to join the PIMS cells