Minutes RF structure meeting 17.04.2009
F. Gerigk, J. Stovall, G. DeMichele, F. Grespan
HOM
- Simulation results on the HOM effect for different code inputs are ready in a paper for PAC09 (FrankGerigk). (Link FR5REP053.pdf)
PIMS
- The Metrologie Service did the first analysis of the e-beam welding test made by Soltan Institut (PL):
- PIMS prototype building postponed to March 2010 for a problem with the workshop machine.(FrankGerigk)
DTL
- Power coupler: new Power Coupler dimension for DTL is under checking with different simulation methods in MWS (GiovanniDeMichele)
- Bead pull measurements show that Cold Model needs to be realigned (probably disassembled) in order to validate first PC stabilization results from the equivalent circuit. (FrancescoGrespan)
--
FrancescoGrespan - 22 Apr 2009