F. Gerigk, J-M. Giguet, G. T. Papadaki, S. Ramberger, K. Schirm, R. Wegner, P. Ugena-Tirado
CCDTL (F. Gerigk)
DTL (S. Ramberger)
- The girder T1S1 is in the final machining stage for the DT holes. Metrology results for the pre-machined girder T1S1 are expected for 23.11.
- 7 drift tubes have been completed with weld 4.
- The tank segment T1S1 is cleaned and ready for copper plating. The surface treatment workshop decided to change the copper plating bath.
PIMS (R. Wegner)
- The last set of copper discs for the PIMS series has arrived at CERN and will be shipped to Poland in January.
- The 2 test rings have been completely welded in Julich and will be transported to Poland by an external company.
- The rough machining and thermal 1st treatment of the 1st waveguide ring were successful, the ellipticity is with roughly 0.2 mm (max-min) well within the allowed tolerance of 0.4 mm (see attachment Ring_Wave_Guide_-_SPLACPMZ0016p8.pdf)
--
RolfWegner - 17-Nov-2011