F. Gerigk, S. Ramberger, R. Wegner, G. DeMichele , and M. Schuh

General

  • Joint meetings with CLIC RF group in the future

CCDTL

  • Meeting at VNIITF (Snezhinsk) where work progress and status was reported

RF –Window

  • Proposal for an alternative design
DTL

PIMS

  • Structure simulations completed, technical drawings are under preparation
  • Materials are partly ordered and rest will be ordered next week
  • Bunker design is official approved
  • Cooling pieces are ordered

HOM

  • Journal paper under preparation

-- MarcelSchuh - 20-Aug-2010