F. Gerigk, S. Ramberger, R. Wegner, G. DeMichele , and M. Schuh

General

  • Joint meetings with CLIC RF group in the future

CCDTL

  • Meeting at VNIITF (Snezhinsk) where work progress and status was reported

RF –Window

  • Proposal for an alternative design
DTL
  • Summary HP test
  • Specs. for girders and cavities will be completed next week
  • Material for girders and inserts are ordered
  • Drift tube tests are ongoing
  • Drift tube drawings approved
  • Q tests next week
  • Bulletin article: The invention that is shaping Linac4

PIMS

  • Structure simulations completed, technical drawings are under preparation
  • Materials are partly ordered and rest will be ordered next week
  • Bunker design is official approved
  • Cooling pieces are ordered

HOM

  • Journal paper under preparation

-- MarcelSchuh - 20-Aug-2010


This topic: SPL > WebHome > Linac4Web > RFStructureMeetings > Minutes20August2010
Topic revision: r1 - 2010-08-20 - MarcelSchuh
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright