Minutes RF structure meeting 23.04.2009
F. Gerigk, S. Ramberger, G. DeMichele, F. Grespan
PIMS (
FrankGerigk)
- Welding Test (Soltan Institute): the welding test has been a full success. For the series production a welding more deep than 7 mm has been proposed, in order to avoid that bubbles at the bottom of the welding can connect to the tank vacuum and create virtual leaks.
- Workshop meeting 23/04:
- complete machining of the central cell, ready to be brazed
- small changes in the drawings
- SCHEDULE:
- December 2009: machining done
- March 2010: Low Power Test
- May/June 2010: final assembly
HOM
- 25-26 June 2009: workshop on HOMs for SPL.
DTL
- Prototype vacuum: because of the chemical processing, the mild steel tank is now degassing from the layer under the copper plating.(SuitbertRamberger)
- Power Coupler:(GiovanniDeMichele)
- comparison of Beta (coupling parameter) computed with 2 simulation methods -> 10% safety margin for simulation results
- MWS and HFSS give different frequency detuning due to the wave-guide -> check with measurements on the Prototype
- Cold Model realigned by RF workshop, and reassembled. First bead-pulling gives a field more flat, but still +/- 20% error for some gaps. Next step is changing the bead to reduce the noise. (FrancescoGrespan)
- Paper on the DTL prototype is ready for PAC09. FR5REP054.pdf
--
FrancescoGrespan - 27 Apr 2009