Minutes RF structure meeting 23.04.2009

F. Gerigk, S. Ramberger, G. DeMichele, F. Grespan

PIMS (FrankGerigk)

  • Welding Test (Soltan Institute): the welding test has been a full success. For the series production a welding more deep than 7 mm has been proposed, in order to avoid that bubbles at the bottom of the welding can connect to the tank vacuum and create virtual leaks.
  • Workshop meeting 23/04:
    • complete machining of the central cell, ready to be brazed
    • small changes in the drawings
  • SCHEDULE:
    • December 2009: machining done
    • March 2010: Low Power Test
    • May/June 2010: final assembly

HOM

  • 25-26 June 2009: workshop on HOMs for SPL.

DTL

  • Prototype vacuum: because of the chemical processing, the mild steel tank is now degassing from the layer under the copper plating.(SuitbertRamberger)
  • Power Coupler:(GiovanniDeMichele)
    • comparison of Beta (coupling parameter) computed with 2 simulation methods -> 10% safety margin for simulation results
    • MWS and HFSS give different frequency detuning due to the wave-guide -> check with measurements on the Prototype
  • Cold Model realigned by RF workshop, and reassembled. First bead-pulling gives a field more flat, but still +/- 20% error for some gaps. Next step is changing the bead to reduce the noise. (FrancescoGrespan)
  • Paper on the DTL prototype is ready for PAC09. FR5REP054.pdf

-- FrancescoGrespan - 27 Apr 2009

Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r3 - 2009-04-29 - FrancescoGrespan
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright