F. Gerigk, J-M. Giguet, S. Ramberger, K. Schirm, R. Wegner
DTL (S. Ramberger)
• Metrology results after correction of tank
T1S1 of CADINOX are expected on Monday 29 August 2011.
• Supplier of girder
T1S2 is currently blocked as we are waiting for metrology results of the short prototype girder from CERN metrology. They are expected for Monday 29 August 2011.
• Further 10 drift tube sets (without stems - required later) from DMP arrived at CERN on 12 August 2011.
• Welding of the first batch of 9 drift tubes to start on 30 August 2011.
--
RolfWegner - 26-Aug-2011