F. Gerigk, S. Ramberger, R. Wegner, P. Tirado, M. Schuh
SPL
- SPL prototype cavity production delayed by 5 month - see SPL Cavity WG meeting (http://indico.cern.ch/event/102075
)
- No common tendering for klystrons with ESS
- Modulator: pre tendering finished
Linac4
- H- Source: currents up to 80mA measured, emittance measurements still to do
DTL
- Discussion on DTL assembly: equipment to align tanks to each other and manufacturing of connection parts
PIMS
- Documents for contract with Soltan Institute ready for signature next week
- Technical specifications changed and new material added
- Material has arrived
- WG-Tuner simulations with cavity
HOM
- Redone ESS simulations with new code version. Beam dynamics in 1.3GHz linac is more stable now.
--
MarcelSchuh - 28-Jan-2011