F. Gerigk, S. Ramberger, G. DeMichele , P. Tirado
Linac4
- accelerating structures high power test
- dedicated place in bld 150 and/or SM18 updating under discussion
- test stand in bld 112 seems to be a backup solution
Buncher cavity
- Performed high power test (Pcav=23kW): NO problems noticed in conditioning
DTL
- Drift tube from Bilbao
- hydrocarbon contamination found in inside surface; silicone found on outside surface
- at least outgassing of electroforming copper surface to be done
- Corrosion test on the anodising magnet matrix: results in almost 3 weeks
- Prototype high power test
- klystron ELIA under conditioning
- vacuum leak after the installation of the magnet in the LE end-cone: planned leak test on Monday; likely end-cone to be re-machined
PIMS
- Welding on the prototype almost finished
- Reduction of the tickness of the waveguide (under vacuum) and waveguide coupler under study
- Simulations on modules ongoing
- Agreements for the production with Juelich and Poland ongoing
- Prototype high power test
- likely the test will be done in the 3MeV test stand area: shielding for x-rays under consideration
--
GiovanniDeMichele - 31-May-2010