F. Gerigk, J-M. Giguet, S. Ramberger, K. Schirm, R. Wegner, P. Ugena-Tirado
Linac4 (F. Gerigk)
- reliability run 2nd half of 2014, ready for connection end of 2014, beginning 2015,
- 20-25 mA of protons have now been measured in the LEBT, around 40 mA out of the source,
- RF meas on RFQ module 2 ok, as before the brazing,
- Serge needs to use some of the spare copper to repair the last module, then there is not enough left to build a complete section. However , A. Pisent still has some spare from the TRASCO RFQ, which could be made available,
CCDTL (F. Gerigk)
- 4 DTs of tank 3 are cut, the rest this week, then module 2 will be put back on the support
- *material for support: * last seven pieces will be cut next Monday, JM has prepared delivery list, which is forwarded to Alexey,
- pumping group is in Novosibirsk,
- phone discussion on support geometry: decided to optimize the slots length (basically the length by which cavity 1 and 3 can be moved with respect to cavity 2
- technical specs support are approved,
- Transfer of funds: Sarov have finished their report, it needs to be decided how much money they get for it.
India collaboration (F. Gerigk)
- India asking to make altogether 4 addenda for couplers, jacks and respective prototyping,
- they are ready to send a coupler prototype, which was built with Indian funds,
- addendum for coupler and ion pumps was checked and sent back to us,
- O. Brunner ready to buy the waveguide tape, which was made in India and will give a commercial cost estimate in the coming days,
- received price estimate on ion sputter pumps from vacuum group,
- sending of coupler material is prepared, waiting for green light from customs (Karl), this way we can insist on having 6 months construction time.
Coupler (F. Gerigk)
- technical specifications are approved,
- drawings were revised: no more threaded flanges and modification on the piston tuner tube, drawings were sent to Purushottam
Jacks (F. Gerigk)
- 4 sets of jacks and nuts have been ordered in industry to be sent to India for prototyping,
Movable tuners (F. Gerigk)
- preparing price enquiry for guiding systems,
- Yves found one British company with exactly the same product but in mild steel instead of stainless, asking for a price for SS
- 2/3 of the material for flanges onto which the bellows are welded has arrived at CERN, remainder within 6 weeks
DTL (S. Ramberger)
- Tank T1S1 has been completed at CADINOX and is being sent to CERN today.
- 9 drift tubes have been assembled at the workshops up to weld 3. Metrology results are good.
SM18 – Linac4 test stand (R. Wegner)
- The modulator has been installed, the klystron gun will be upgraded next week
PIMS (R. Wegner)
- NCBJ: The waveguide ring is being measured in the metrology lab after the 1st heat treatment and is being machined (2nd rough machining)
- NCBJ: Brazing of 3 GHz structure for NCBJ in the new furnace
--
RolfWegner - 30-Sep-2011