klystron partitioning Linac4

cavity type number LEP klystron 352 MHz high-power klystron Timestamp
RFQ 1 1 - 13 August 2007
DTL 1 1 - 13 August 2007
DTL 2,3 - 2 13 August 2007
CCDTL 1-7 7 - 13 August 2007
PIMS 1-4 4 - 13 August 2007
PIMS 5-12 - 4 13 August 2007
total   13 6  

power requirements at the cavity level

cavity peak power [kW] Comment Timestamp
RFQ 537 Superfish + 20% + beam 26 May 2009
DTL1 1000 ZTT*0.8 + beam 26 May 2009
DTL2 2000 ZTT*0.8 + beam 26 May 2009
DTL3 2000 ZTT*0.8 + beam 26 May 2009
CCDTL1 960 Superfish (incl. stems) + 20% + beam 26 May 2009
CCDTL2-7 1000 Superfish (incl. stems) + 20% + beam 26 May 2009
PIMS1-12 1000 Superfish ZTT - 30% (22/26% for Linac4/SPL), incl. everything 26 May 2009

Ion species H-   10 August 2007

waveguides & auxiliary equipment

  • CPI coaxial window for 352 and 704 MHz operation: link
  • AFT RF load for half-height wave-guides, 352 MHz: link (restricted access)

SPL klystrons (under construction)

  • Thales TH2168, 5 MW, 450 kW CW, 805 MHz (restricted access)

-- FrankGerigk - 18 Jun 2007