klystron partitioning Linac4

cavity type number LEP klystron 352 MHz high-power klystron Timestamp
RFQ 1 1 - 13 August 2007
DTL 1 1 - 13 August 2007
DTL 2,3 - 2 13 August 2007
CCDTL 1-7 7 - 13 August 2007
PIMS 1-4 4 - 13 August 2007
PIMS 5-12 - 4 13 August 2007
total   13 6  

power requirements at the cavity level

cavity peak power [kW] Comment Timestamp
RFQ 537 Superfish + 20% + beam 25 September 2008
DTL1 950/1040 ZTT (w.o. stems/incl. stems)- 20% + beam 25 September 2008
DTL2 1920/2130 ZTT (w.o. stems/incl. stems)- 20% + beam 25 September 2008
DTL3 1850/2020 ZTT (w.o. stems/incl. stems)- 20% + beam 25 September 2008
CCDTL1 960 Superfish (incl. stems) + 20% + beam 25 September 2008
CCDTL2-7 1000 Superfish (incl. stems) + 20% + beam 25 September 2008
PIMS1-12 970 - 1020 Superfish ZTT - 30% (22/26% for Linac4/SPL), incl. everything 25 September 2008

Ion species H-   10 August 2007

waveguides & auxiliary equipment

  • CPI coaxial window for 352 and 704 MHz operation: link
  • AFT RF load for half-height wave-guides, 352 MHz: link (restricted access)

SPL klystrons (under construction)

  • Thales TH2168, 5 MW, 450 kW CW, 805 MHz (restricted access)

-- FrankGerigk - 18 Jun 2007

Edit | Attach | Watch | Print version | History: r8 < r7 < r6 < r5 < r4 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r7 - 2008-09-25 - FrankGerigk
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    SPL All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright