klystron partitioning Linac4
cavity type
number
LEP klystron
352 MHz high-power klystron
Timestamp
RFQ
1
1
-
13 August 2007
DTL
1
1
-
13 August 2007
DTL
2,3
-
2
13 August 2007
CCDTL
1-7
7
-
13 August 2007
PIMS
1-4
4
-
13 August 2007
PIMS
5-12
-
4
13 August 2007
total
13
6
power requirements at the cavity level
cavity
peak power [kW]
Comment
Timestamp
RFQ
537
Superfish + 20% + beam
26 May 2009
DTL1
1000
ZTT*0.8 + beam
26 May 2009
DTL2
2000
ZTT*0.8 + beam
26 May 2009
DTL3
2000
ZTT*0.8 + beam
26 May 2009
CCDTL1
960
Superfish (incl. stems) + 20% + beam
26 May 2009
CCDTL2-7
1000
Superfish (incl. stems) + 20% + beam
26 May 2009
PIMS1-12
1000
Superfish ZTT - 30% (22/26% for Linac4/SPL), incl. everything
26 May 2009
Ion species
H-
10 August 2007
waveguides & auxiliary equipment
CPI coaxial window for 352 and 704 MHz operation:
link
AFT RF load for half-height wave-guides, 352 MHz:
link
(restricted access)
SPL klystrons (under construction)
Thales TH2168, 5 MW, 450 kW CW, 805 MHz (restricted access)
--
FrankGerigk
- 18 Jun 2007
E
dit
|
A
ttach
|
Watch
|
P
rint version
|
H
istory
: r8
<
r7
<
r6
<
r5
<
r4
|
B
acklinks
|
R
aw View
|
WYSIWYG
|
M
ore topic actions
Topic revision: r8 - 2009-05-26
-
FrankGerigk
Log In
SPL
SPL Web
Create New Topic
Index
Search
Changes
Notifications
Statistics
Preferences
TWiki Text Formatting Rules
Twiki Registration
EventCalendar
3MeV Test Stand
Linac4Web
SplWeb
RFpowerPages
RestrictedInformation
Cern Search
TWiki Search
Google Search
SPL
All webs
Copyright