technical information | meetings | planning |
---|---|---|
Installation Layout![]() |
Meeting minutes, technical coordination![]() |
Planning |
Technical Infrastructure![]() |
Meeting minutes, test stand installation![]() |
|
Cabling![]() |
||
Test Stand naming convention![]() |
||
safety | ||
The Linac4 Test Stand Safety File![]() |
||
activities | people and groups | schedule |
---|---|---|
Preparing the RFQ transfer to the Linac4 Tunnel | V. Bretin, BE/RF, BE/BI, TE/VSC, EN/CV | week 25 |
Install the RFQ in the Linac4 tunnel | V, Bretin, Transport, Survey, TE/VSC | weeks 26 to 29 |
Install the MEBT line in the Linac4 tunnel | V, Bretin, Transport, Survey, TE/VSC | week 31 to 32 |