Linac4 3 MeV Test Stand
Operation with 3 MeV beam has been completed
Calendar of Activities
activities |
people and groups |
schedule |
|
|
|
Preparing the RFQ transfer to the Linac4 Tunnel |
V. Bretin, BE/RF, BE/BI, TE/VSC, EN/CV |
week 25 |
Install the RFQ in the Linac4 tunnel |
V, Bretin, Transport, Survey, TE/VSC |
weeks 26 to 29 |
Install the MEBT line in the Linac4 tunnel |
V, Bretin, Transport, Survey, TE/VSC |
week 31 to 32 |
The area is now considered of restricted access (with dosimeter). Please contact C. Rossi (160830) to organize the access of personnel without dosimeter.
updated by C. Rossi on 14 June 2013