Linac4 3 MeV Test Stand

technical information meetings planning
     
Installation Layout Meeting minutes, technical coordination Planning
Technical Infrastructure Meeting minutes, test stand installation  
Cabling    
Test Stand naming convention    
     
safety    
     
The Linac4 Test Stand Safety File    
     

Operation with 3 MeV beam has been completed

Calendar of Activities

activities people and groups schedule
     
Preparing the RFQ transfer to the Linac4 Tunnel V. Bretin, BE/RF, BE/BI, TE/VSC, EN/CV week 25
Install the RFQ in the Linac4 tunnel V, Bretin, Transport, Survey, TE/VSC weeks 26 to 29
Install the MEBT line in the Linac4 tunnel V, Bretin, Transport, Survey, TE/VSC week 31 to 32

The area is now considered of restricted access (with dosimeter). Please contact C. Rossi (160830) to organize the access of personnel without dosimeter.

updated by C. Rossi on 14 June 2013

Topic attachments
I Attachment History Action Size Date WhoSorted ascending Comment
GIFgif TestStandPlanning3101.gif r1 manage 29.6 K 2013-01-31 - 18:31 GiuliaBellodi  
GIFgif TestStandPlanningLast.gif r2 r1 manage 41.1 K 2013-02-14 - 17:54 GiuliaBellodi  
GIFgif TestStandPlanninglast.gif r1 manage 39.8 K 2013-02-11 - 15:54 GiuliaBellodi  

This topic: SPL > WebHome > TestStand
Topic revision: r53 - 2013-06-14 - CarloRossi
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright