activities | people and groups | schedule |
---|---|---|
Ion Source beam setting up | J. Lettry, R. Scrivens & team | weeks 2 to 6 |
Tuning of Linac4 RFQ | C. Rossi, CEA Team | weeks 4 to 5 |
Vacuum installation and tests on Linac4 RFQ | J. Hansen & team | weeks 2 to 6 |
Linac4 RFQ RF Conditioning | C. Rossi & Linac Team | starting from week 7 |