Topic | Details | Deadline |
---|---|---|
Integration of LIU Systems | Prepare lists of new systems to be integrated: * Identification and definition of items * Identification and definition of processes/procedures * Required algorithms * Software readiness *… Definition of integration meetings with equipment groups where required |
April 2019 |
List of Software | Identification of software needs: * Either for integration of new systems or improved integration of existing ones * Additional software requirements: algorithms, processes * Resources: sufficient man power available / potential synergies between machines to be exploited? |
June 2019 |
Planning HWC + Dry Runs | * Planning + check lists for LBE run * Planning for the rest of the complex (including DSO tests, power permits, resources, …) * HWC check lists |
June 2019 December 2019 3 Months before start of HWC |
List of performance tracking parameters | Definition of observables to be tracked: * machine-specific or already beam centric (cross-machine) if available * Collection of analysis algorithms/tools |
July 2019 |
IST Plannnig | Establish lists of ISTs in collaboration with equipment groups EN-ACE + OP: final IST lists and conditions (e.g. access system SPS, CV availability, …) |
June 2019 September 2019 |
Injector schedule: List of beam readiness and FT facility start up dates |
Focus on FT community. Define: * readiness dates with initial beam parameters * timeline for intensity ramp-up in 2021 * max. intensity required in 2021 First iteration Refined version |
July 2019 December 2019 |
FESA Class readiness dates | * Establish list based on software needs. * Negotiate readiness dates with groups * Estimate for OP developments required |
August 2019 |
Christmas shutdown 2020/2021 | * Identification of critical items * Identification of piquet requirements * Definition of equipment state during Xmas period * ... |
December 2019 |
Beam commissioning planning | Detailed planning with resources | February 2020 |
Origin | Follow-up | Status |
---|---|---|
6 - January - 2020 https://indico.cern.ch/event/874715/![]() |
||
PS(B) DSO Tests and EPC Update on POPS(B) Tests and Switchyard | Discuss needs for DSO tests in LEIR as they will be different | |
Ensure sufficient OP personnel will be available for all patrols prior to DSO tests | ||
Confirm machines will be cleaned and closed before patrols start | ||
Discuss overlap between SPS ISTs and POPS commissioning | ||
YETS 20/21 Considerations | Determine piquet needs for Linac4 over the stop | |
13 - December - 2019 https://indico.cern.ch/event/869773/![]() |
||
Dry Runs: PSB | Determine if an application is required for injection line matching | |
Make tests of extraction system a specific Dry Run | ||
Complete definition of deadlines | ||
Hardware Commissioning: PSB | Cross correlate needs for RF personell for different accelerators | |
Hardware Commissioning: PS | Confirm MSC test details | |
Confirm dates of EPC tests | ||
Discuss overlap in demands on EPC personell between PS and SPS | ||
6 - December - 2019 https://indico.cern.ch/event/868112/![]() |
||
Dry Runs: PS | Add new injection septum to the dry run planning | |
Include virtual correctors in the new optics model | ||
AOB: Status of ISTs and Next Steps | Rearrange EPC tests for PSB and PS to compensate for overlap in resources | |
Discuss overlap between injectors and anti-proton machines | ||
29 - November - 2019 https://indico.cern.ch/event/865764/![]() |
||
YETS 20/21 | The availability of experts for the restart of beam needs to be confirmed | |
Confirm necessary Linac4 maintenance, and possible impact on restart | ||
Confirm specific requirements for equipment groups for the restart, to determine minimum time necessary | ||
Determine if there is a benefit to running the Linac4 ion source over the shutdown period | ||
Beam Performance Tracking Status | Investigate possibility of merging injector and LHC performance tracking | |
Check List Tool | Investigate the possibility of moving to a commercial product | |
Long term support for other tools to be determined | ||
15 - November - 2019 https://indico.cern.ch/event/862953/![]() |
||
Approval of Minutes and Matters Arising | Template on CO requirements to be filled in by commissioning working groups | |
SPS Dry Runs | Relocate SPSQC test to avoid clash with BI tests | |
Additional details required for SBDS test | ||
CO requests details of Dry Runs to be stored in a central location | ||
1 - November - 2019 https://indico.cern.ch/event/859585/![]() |
||
PSB Individual System Tests | Confirm access controls for TE-MSC high voltage tests | |
Confirm no activity in PSB surface buildings during TE-EPC tests | ||
Check if TE-ABT tests can be included in TE-EPC risk analysis | ||
Confirm that POPS-B tests do not require controls | ||
PS Individual System Tests | Define controls requirements to ensure adequate infrastucture for all tests | |
Finalise BE-RF IST planning | ||
Increase margine for F61 tests | ||
Clarify BE-OP manpower during test periods | ||
AOB | Clarify controls requirements for equipments groups for all tests | |
18 - October - 2019 https://indico.cern.ch/event/855026/![]() |
||
Injector Schedule 2020/2021 | Determine slip-stacking commissioning period | |
Discuss MD organisation during 2021 | ||
Commissioning organisation during 2020 | Consider putting ISTs under mandate of EN-ACE technical coordination meetings | |
4 - October - 2019 https://indico.cern.ch/event/851834/![]() |
||
Approval of Minutes and Matters Arising | Distribute IST procedure template | |
HWC Planning - PS | Define OP manpower requirements during the HWC | |
HWC Planning - SPS | Finalise details HWC tests that still need additional information | |
Consider possibility of manpower being required during IST period | ||
HWC Planning - IONS | Organise meetings concerning Linac3 safety aspects | |
27 - September - 2019 https://indico.cern.ch/event/845794/![]() |
||
Approval of Minutes and Matters Arising | Complete IST schedule for all machines | |
CO Feedback on Beam Performance Tracking | Discuss how API will handle Beam IDs, Beam Instance IDs, and BCD Stamps to correctly identify cycles | |
Determine if web TIMBER can give suitable performance for displaying beam data | ||
Linac4 3 MeV Run | Repeat measurements of 2 MHz ripple at higher energy | |
20 - September - 2019 https://indico.cern.ch/event/845792/![]() |
||
Approval of Minutes and Matters Arising | Define a cross-complex system for organisation during the IST period | |
FESA Class Readiness - PS | Ensure FESA2 classes are updated to FESA3 and additional classes are completed | |
Consider formalising the monitoring of class developments | ||
FESA Class Readiness - SPS | Identify method to allow more than 8 injections | |
AOB | Consider revisiting FESA classes in the future | |
AOB - IST Planning | Finalise how removal of lockouts will be handled | |
Clarify access state during IST period, and decide who should be in the CCC | ||
6 - September - 2019 https://indico.cern.ch/event/844660/![]() |
||
Approval of Minutes and Matters Arising | Discuss transition from commissioning coordination meeting to beam performance meeting | |
Linac4 IST Report | Define final test procedures for phase 4 of ISTs | |
Consider weekly FOM type meeting for after LS2 to discuss ISTs in all machines, with a daily morning meeting for that days ISTs | ||
Review all test procedures in Commissioning Working Groups to identify safety related ISTs, which require more detailed procedures | ||
Discuss possibility of requiring OP group in CCC throughout IST period | ||
FESA Class Readiness - LEIR | Identify necessary software developers | |
23 - August - 2019 https://indico.cern.ch/event/841490/![]() |
||
Approval of Minutes and Matters Arising | Collate IST and HW commissioning schedules in preparation for LS2 day | |
Compile prototype beam availability schedule based on each injector's schedule | ||
Beam Readiness Dates - SPS | Define when fixed target ion beams will be available | |
Specify ion beam commissioning slots as part of schedule | ||
Include expected 12 bunch beam availability in schedule | ||
Confirm number of days of beam available for HiRadMat and AWAKE | ||
Beam Performance Tracking Outcome | Define requirements for CO | |
Discuss how to approach performance tracking for non-operational beams | ||
Organise a meeting between the BCWG and CO to discuss requirements | ||
Define suitable metrics for each beam | ||
9 - August - 2019 https://indico.cern.ch/event/839130/![]() |
||
Beam Readiness Dates - PSB | Cross check with PS schedule | |
Beam Readiness Dates - Ions | Determine likely schedule of studies in the SPS | |
26 - July - 2019 https://indico.cern.ch/event/836825/![]() |
||
Status of IST Scheduling | PS and SPS first draft to be completed | |
Include BTP line information in PS schedule | ||
Give deadline to experimental areas for IST scheduling | ||
AOB: Synergies for the Different TFB Systems | Identify software developer to collaborate with machine experts | |
Discuss required FESA and firmware modifications with RF group | ||
Confirm responsible person for each TFB with RF | ||
12 - July - 2019 https://indico.cern.ch/event/830277/![]() |
||
28 - June - 2019 https://indico.cern.ch/event/833199/![]() |
||
Beam performance tracking - Ions | Create a document detailing the requirements for performance tracking | |
14 - June - 2019 https://indico.cern.ch/event/824431/![]() |
||
Status of the reference measurement system | Clarify status of application support in the long term | |
Make raw data from JAPC objects recoverable after change of Java libraries | ||
Consider interface between NXCALS and reference tool for data storage | ||
Linac3/LEIR Status of ISTs | Migrate Linac3 schedule from Excel to Microsoft Project | |
Confirm responsible persons for all tests | ||
Finish defining test and dates for missing items | ||
Investigate possibility of exporting data from Excel to the checklist tool | ||
Determine how accesses will be organised during source tests | ||
Ensure relevant items from Linac3/LEIR schedule are included in Switchyard schedule | ||
31 - May - 2019 https://indico.cern.ch/event/823325/![]() |
||
Status of the IST list for all machines | Discuss schedule of switchyard closure during ISTs | |
Clarify PS ABT equipment ISTs in relation to switchyard closure | ||
Define deadlines and developers for software synergies | ||
Provide EN-ACE with procedures for ISTs and consider creating EDMS documents | ||
23 - May - 2019 https://indico.cern.ch/event/821925/![]() |
||
Equipment Integration PS | Investigate possibility of making BGI applications uniform across injectors | |
Investigate possibility of making WS applications uniform across injectors | ||
Investigate better sharing of TT2 steering between PS and SPS | ||
17 - May - 2019 https://indico.cern.ch/event/819356/![]() |
||
Approval of Minutes and Matters Arising | Prepare HW commissioning plans for the LBE line run | |
Equipment integration Linac4 | Follow up distribution of "transactional settings" to relevant FESA classes | |
Equipment integration PSB | Investigate possibility of including PSB injection mechanism in injection autpilot application | |
Collect FESA readiness dates | ||
3 - May - 2019 https://indico.cern.ch/event/817498/![]() |
||
Approval of Minutes and Matters Arising | Review possibilities for planning tool, considering MALT | |
Confirm final details for Linac4 ISTs | ||
Equipment Integration Linac3/LEIR | Define responsible person for new software tools | |
Prioritise list of desired software tools in case of insufficient manpower | ||
Equipment integration SPS | Define details of RF dry runs | |
Define details of software development and equipment testing, target end of August | ||
Investigate overlaps between SPS and PS BGI applications | ||
11 - April - 2019 https://indico.cern.ch/event/810607/![]() |
||
Approval of Minutes and Matters Arising | Confirm impact of IST period on LBE line run | |
Introduction to EN-ACE Planning Tool | Continue discussions of suitable planning tool for HW and beam commissioning scheduling | |
Investigate possibility of providing post-LS2 schedule information to EN-ACE for resource checking and final schedule construction | ||
Consider including LHC commissioning with injectors due to overlap of experts | ||
29 - March - 2019 https://indico.cern.ch/event/803331/![]() |
||
Switchyard and POPS(B) tests | Confirm schedule and safety of ISTs with EPC | |
Organise ventilation of Linac3 during testing | ||
Confirm extent of powering and possible safety needs with work proximate to power cables | ||
Ion transfer line tests need to include testing of BI equipment | ||
Confirm availability of services during early SWY closure | ||
Finalise list of CO requrements for ISTs | ||
ISTs | Update IST table to include LEIR and Linac3 | |
Establish a safety protocol for access during IST period | ||
Confirm with DSOs what (if any) tests are required for each machine at the start of IST period | ||
15 - March - 2019 https://indico.cern.ch/event/803083/![]() |
||
Outcome of the LIU Workshop | Treat resource loaded and co-activityplanning | |
Decide on a HWC planning tool | ||
Discuss commissioning requirements of experiments | ||
25 - February - 2019 https://indico.cern.ch/event/798112/![]() |
||
Switchyard Access | Confirm with EPC if POPS or POPSB commissioning will come first | |
Confirm current master schedule is suitable for EPC | ||
Include ION SWY polarity tests master schedule and approve with LS2 committee | ||
Establish a schedule in case the POPS containers do not arrive on time | ||
18 - January - 2019 https://indico.cern.ch/event/785476/![]() |
||
PSB Beam Commissioning | Review HW and beam commissioning schedules in context of equipment experts availability | |
Consider making commissioning EDMS documents in all injectors as in the PSB | ||
Prepare beam availability schedule for each experimental facility |
Origin | Follow-up | Status |
---|---|---|
23 -November - 2018 https://indico.cern.ch/event/775497/![]() |
||
Linac4 LBE Line Run | Finalise scheduling plans for out-of-hours work | |
Schedule presentation from Linac 4 RF expert | ||
16 -November - 2018 https://indico.cern.ch/event/774197/![]() |
||
SPS Beam Commissioning | Ensure schedule accommodates needs of BI (and possibly other systems) for 25ns trains | |
Determine prioritisation of items | ||
Modify schedule to ensure adequate scrubbing time | ||
Rename "scrubbing" as "conditioning" | ||
Consider adding specified 24-hour access period for planning access | ||
Include relevant equipment tests with beam (e.g. BLMs) | ||
Integrate BI testing and commissioning schedule with beam schedule | ||
9 -November - 2018 https://indico.cern.ch/event/771454/![]() |
||
LEIR Reference Measurements | Modify reference measurements tool to allow a checklist of measurements to be taken | |
Include long term variations in performance in reference measurements | ||
AOB | Investigate potential benefits of "super-settings" and amount of work required to implement them | |
Investigate possible complex wide improvements to operation (e.g. cycle defintion approach) | ||
2 -November - 2018 https://indico.cern.ch/event/764260/![]() |
||
LIU-PSB Integration Plans | Provide a specification for beam quality tracking functionality in new WS application | |
Investigate copying the functionality of the PS MPS editor application for use in the PSB, including discussions with Settings Management WG | ||
12 - October - 2018 https://indico.cern.ch/event/760162/![]() |
||
General discussion | Discuss general approach to reference measurements reducing dependence on key individuals | |
Discussion over best practice for acquiring and storing references based on experience in each machine | ||
Bring operators (or a subset) into meetings where practical | ||
Ion reference measurements in PS and SPS | ||
5 - October - 2018 https://indico.cern.ch/event/757692/![]() |
||
LIU SPS RF | Determine required real-time information and coordinate with CO | |
Investigate amount of required information from PS for Phase Loop mask and overlap with BQM | ||
Produce detailed list of cycles required for commissioning in order | ||
Discussions between OP and RF of what diagnostics and controls to make available in the CCC | ||
LIU PS Injection Region | Determine suitable (operational) injection matching procedure | |
General Discussion | Meeting between machine coordinators to discuss new controls requirements | |
Detail requirements of operators during shutdown | ||
21 - September - 2018 https://indico.cern.ch/event/757690/![]() |
||
LIU SPS Beam Dump | Discuss requirements for real time data distribution | |
Consider possibility of planning contingency time in schedule | ||
General Discussion | Discuss a schedule for required services | |
Consider coordinating hardware commissioning schedule with availability of equipment experts | ||
31 - August - 2018 https://indico.cern.ch/event/743773/![]() |
||
LINAC4 Beam Commissioning | Beam expected to be optimised by 28 - September | |
Add daily debriefing to the eLogbook | ||
Reference Measurement Tool | Test of API in other machines and applications | Reported to be non-trivial by PSB |
Investigate possibility of storing ACQ data along with CCV | ||
Investigate data links for large files | ||
To be tested by as many users as possible | ||
24 - August - 2018 https://indico.cern.ch/event/743773/![]() |
||
Matters Arising | Test possibility of using PSB h=1 to make an MTE-like at the start of commissioning for the SPS | |
Linac4 Hardware Commissioning | Try to enable checklist tracking of commissioning progress of RF and ion source | |
SPS Reference Measurements | Include ion beams in reference planning | |
3 - August - 2018 https://indico.cern.ch/event/743761/![]() |
||
PS Reference Measurements | Saving AQN and CCV together | |
Tomoscope reference and live measurement in parallel | Under discussion with Tomoscope application developer | |
Automated connection of OASIS signals | Being investigated with current OASIS API | |
Discussion | Discussion of additional requirements for each machine - e.g. OASIS modifications | |
EPC measurements of current in power converters to compare with AQN and CCV | ||
27 - July - 2018 https://indico.cern.ch/event/742681/![]() |
||
LINAC3 Reference Measurements | Diagnostics for LINAC3 using LEIR tools - e.g. Schottky | |
Absolute beam energy measurement in spectrometer line | ||
Effect of steering on transmission into LEIR and possibility of correction | ||
PSB Reference Measurements | Investigate the possibility of checking aperture restriction in Ring 2 with beam | |
15 - June - 2018 https://indico.cern.ch/event/733190/![]() |
||
Discussion | Physics planning post-LS2 and impact on beam commissioning priorities | |
Previous meetings https://indico.cern.ch/category/9633/![]() |
||
Super settings for generation and trim (Delphine) | ||
LINAC4 responsibilities: what is happening during LS2? | ||
New timing system approach: where shall/should we go | ||
Reference measurements end of 2018 for after LS2. How to store reference measurements? New framework? | ||
Super table and beam parameter statistics | ||
Check list tool: add additional requirements for post LS2. Prepare func spec | ||
Software synergies between machines | ||
Manpower requirements for injector settings management implementation (Delphine) | ||
Expert shifts during start-up? | ||
Ideal length of beam commissioning for all beam types up to high intensity per machine | ||
How to add testing of signal exchange between machines in planning tool? (Readiness of beam type?) | ||
PSB and LINAC4? Commissioning with/of LINAC(2)4. Who is responsible for what? What about check lists and planning? | ||
Organisation of individual system tests: if some should be carried out during hardware commissioning, how much extra time is required for check out? | ||
Which of the individual system tests should be done during hardware commissioning? | ||
Add required state/settings of equipment to test procedure | ||
Organise full de-consignation at end of shutdown | ||
Better cross-coordination, also including LHC for planning and required testing of LINACs (switch yard) | ||
Need hard end of shutdown. No more carry over shutdown work | ||
Define better interface between check lists and ASM |
I | Attachment | History | Action | Size | Date | Who | Comment |
---|---|---|---|---|---|---|---|
![]() |
2018-BCWG.pptx | r1 | manage | 1573.7 K | 2017-12-13 - 15:51 | ReyesAlemanyFernandez |