ATLAS Muon Phase 2 Resources Coordinator Page.


%ATLASLOGO%

ATLAS Muon Spectrometer

Muon Upgrade Phase II


Introduction

Documentation

Major Procurements Via CERN

Item wbs DAI date Institute Total Value (CHF) Total Value () Deliverables Sharing (%) Status
Flat halogen-free cable 5.2.4.5 11/10/2019 T525100 Hong Kong 175,546 159,660 Hong Kong, 100 Completed
Aluminum tubes for sMDT 5.1.1.1 30/01/2020 T525100 UM(Michigan) 408,321 381,680 UM(Michigan), 100 Completed
Connectors for flat cables 5.2.3.1 01/07/2020 T525203 Mainz(BMBF) 20,381 19,162 Mainz(BMBF), 100 Completed
ASD, additional 25 wafers 5.2.1.1 25/06/2020 T525201 MPI 48,579   MPI, 100 Completed
ASD non recurring costs (masks) 5.2.1.1 25/06/2020 T525201 MPI, Mainz(BMBF) 345,100   MPI, 38, Mainz(BMBF) 62 Completed
Gas-Gaps 5.3.1 ongoing       1.000,000   Market Survey started

RPCPrototypes

DAI date Issued by Item Total Value (CHF) Total Value () Share among budgets (CHF)
8651776 24/02/2021 G.Aielli ATLAS RPC's prototypes for phase 2 19500 17679.2 12090 (T529530),7410 (T192700)


-- BaroncelliToni - 2021-06-24

Edit | Attach | Watch | Print version | History: r5 < r4 < r3 < r2 < r1 | Backlinks | Raw View | WYSIWYG | More topic actions
Topic revision: r5 - 2021-07-15 - BaroncelliToni
 
    • Cern Search Icon Cern Search
    • TWiki Search Icon TWiki Search
    • Google Search Icon Google Search

    Sandbox All webs login

This site is powered by the TWiki collaboration platform Powered by PerlCopyright & 2008-2021 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
or Ideas, requests, problems regarding TWiki? use Discourse or Send feedback