Planning Order process
For each delivery, we need to know
- Order Type (Market Survey, Price Enquiry, Tender)
- Equipment Type (N/A, Worker Nodes, Small Disk Servers, Disk Servers, Tape Servers, FC Disks, FC Switches, Head Nodes)
- Customer (free format text)
- Target production date
- Volume announced (in kCHF)
- Number announced
- Volume expected (in kCHF)
- Number expected
- Budget Code
- Announce Date
- FC Date
- FC Action
- Draft Docs
- It Review = Draft Docs + 3 days
- Spec Meeting = IT review + 7 days
- Docs Ready = Spec Meeting + 3 days
- Procedure Out = Docs Ready + 7 days
- Replies Deadline = Procedure Out + 6 weeks
- Replies Opened = Replies Deadline + 1 day
- Replies Analysed = Replies opened + 7 days
- Eval started date = Replies Analysed + 7 days
- Eval finished date = Eval Started + 2 weeks
- FC approval date
- Order date
- Delivery date = Order date + 8 weeks
- Production date (planned) = Delivery date + 4 weeks if CPU or Server